This topic contains a solution. Click here to go to the answer

Author Question: In a PERT network, a/an _____ is the earliest point in time an activity can begin. a. late start b. ... (Read 65 times)

DelorasTo

  • Hero Member
  • *****
  • Posts: 548
In a PERT network, a/an _____ is the earliest point in time an activity can begin.
 a. late start
 b. on time start
  c. early finish
 d. early start
 e. late finish

Question 2

According to Aspinwall, short channels are expected for products with a:
 a. High replacement rate.
  b. High gross margin.
  c. Low time of consumption.
  d. Low adjustment needs.
  e. Low searching time.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Jossy

  • Sr. Member
  • ****
  • Posts: 336
Answer to Question 1

d

Answer to Question 2

B




DelorasTo

  • Member
  • Posts: 548
Reply 2 on: Jun 29, 2018
YES! Correct, THANKS for helping me on my review


meganmoser117

  • Member
  • Posts: 303
Reply 3 on: Yesterday
Great answer, keep it coming :)

 

Did you know?

Methicillin-resistant Staphylococcus aureus or MRSA was discovered in 1961 in the United Kingdom. It if often referred to as a superbug. MRSA infections cause more deaths in the United States every year than AIDS.

Methicilli ...
Did you know?

Persons who overdose with cardiac glycosides have a better chance of overall survival if they can survive the first 24 hours after the overdose.

Did you know?

Opium has influenced much of the world's most popular literature. The following authors were all opium users, of varying degrees: Lewis Carroll, Charles, Dickens, Arthur Conan Doyle, and Oscar Wilde.

Did you know?

In 1864, the first barbiturate (barbituric acid) was synthesized.

Did you know?

There are more nerve cells in one human brain than there are stars in the Milky Way.

For a complete list of videos, visit our video library