Author Question: The fourth phase of the project life cycle involves ________. A) developing the initial ideas of ... (Read 95 times)

Yolanda

  • Hero Member
  • *****
  • Posts: 757
The fourth phase of the project life cycle involves ________.
 
  A) developing the initial ideas of what needs to be done
  B) conducting studies of factors that drive costs and productivity
  C) obtaining workers and equipment to execute plans
  D) training personnel that work in the new assembly unit
  E) preparing a schedule and a design for the assembly process

Question 2

A(n) ________ is a project planning tool which lists the tasks, key resources needed, completion deadlines, and the persons responsible for task completion.
 
  A) work breakdown structure
  B) network technique
  C) work plan
  D) Gantt chart
  E) bar chart



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

kalskdjl1212

  • Sr. Member
  • ****
  • Posts: 353
Answer to Question 1

D

Answer to Question 2

C




Yolanda

  • Member
  • Posts: 757
Reply 2 on: Jul 6, 2018
Thanks for the timely response, appreciate it


covalentbond

  • Member
  • Posts: 336
Reply 3 on: Yesterday
Wow, this really help

 

Did you know?

After 5 years of being diagnosed with rheumatoid arthritis, one every three patients will no longer be able to work.

Did you know?

Prostaglandins were first isolated from human semen in Sweden in the 1930s. They were so named because the researcher thought that they came from the prostate gland. In fact, prostaglandins exist and are synthesized in almost every cell of the body.

Did you know?

Malaria was not eliminated in the United States until 1951. The term eliminated means that no new cases arise in a country for 3 years.

Did you know?

There can actually be a 25-hour time difference between certain locations in the world. The International Date Line passes between the islands of Samoa and American Samoa. It is not a straight line, but "zig-zags" around various island chains. Therefore, Samoa and nearby islands have one date, while American Samoa and nearby islands are one day behind. Daylight saving time is used in some islands, but not in others—further shifting the hours out of sync with natural time.

Did you know?

Hip fractures are the most serious consequences of osteoporosis. The incidence of hip fractures increases with each decade among patients in their 60s to patients in their 90s for both women and men of all populations. Men and women older than 80 years of age show the highest incidence of hip fractures.

For a complete list of videos, visit our video library