What is a critical path? How is a critical path analysis done?
 
  What will be an ideal response?

Question 2

In RFM analysis, an R score of 5 shows that ________.
 
  A) a customer has not made any recent purchases
  B) a customer has bought the most expensive items
  C) a customer has frequently ordered expensive items
  D) a customer has purchased the least expensive items



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

karlss

  • Sr. Member
  • ****
  • Posts: 321
Answer to Question 1

A critical path is a sequence of activities that determine the earliest date by which a
project can be completed. The earliest date is the date determined by considering the longest path
through the network of activities. Paying attention to task dependencies, a planner can compress
tasks as much as possible. Those tasks that cannot be further compressed lie on the critical path.
Microsoft Project and other project-planning applications can readily identify critical path tasks.
Managers can use the critical path to perform critical path analysis. If a task is on the critical
path, and if that task runs late, the project will be late. Hence, tasks on the critical path cannot be
allowed to run late if the project is to be delivered on time. Additionally, tasks not on the critical
path can run late to the point at which they would become part of the critical path. Hence, up to a
point, resources can be taken from noncritical path tasks to shorten tasks on the critical path.
Using critical path analysis, managers can move resources among tasks so as to compress the
schedule.

Answer to Question 2

A




2125004343

  • Member
  • Posts: 566
Reply 2 on: Jul 7, 2018
Gracias!


yeungji

  • Member
  • Posts: 319
Reply 3 on: Yesterday
Thanks for the timely response, appreciate it

 

Did you know?

Critical care patients are twice as likely to receive the wrong medication. Of these errors, 20% are life-threatening, and 42% require additional life-sustaining treatments.

Did you know?

Although puberty usually occurs in the early teenage years, the world's youngest parents were two Chinese children who had their first baby when they were 8 and 9 years of age.

Did you know?

If you could remove all of your skin, it would weigh up to 5 pounds.

Did you know?

The human body's pharmacokinetics are quite varied. Our hair holds onto drugs longer than our urine, blood, or saliva. For example, alcohol can be detected in the hair for up to 90 days after it was consumed. The same is true for marijuana, cocaine, ecstasy, heroin, methamphetamine, and nicotine.

Did you know?

Human neurons are so small that they require a microscope in order to be seen. However, some neurons can be up to 3 feet long, such as those that extend from the spinal cord to the toes.

For a complete list of videos, visit our video library