What is a critical path? How is a critical path analysis done?
 
  What will be an ideal response?

Question 2

In RFM analysis, an R score of 5 shows that ________.
 
  A) a customer has not made any recent purchases
  B) a customer has bought the most expensive items
  C) a customer has frequently ordered expensive items
  D) a customer has purchased the least expensive items



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

karlss

  • Sr. Member
  • ****
  • Posts: 321
Answer to Question 1

A critical path is a sequence of activities that determine the earliest date by which a
project can be completed. The earliest date is the date determined by considering the longest path
through the network of activities. Paying attention to task dependencies, a planner can compress
tasks as much as possible. Those tasks that cannot be further compressed lie on the critical path.
Microsoft Project and other project-planning applications can readily identify critical path tasks.
Managers can use the critical path to perform critical path analysis. If a task is on the critical
path, and if that task runs late, the project will be late. Hence, tasks on the critical path cannot be
allowed to run late if the project is to be delivered on time. Additionally, tasks not on the critical
path can run late to the point at which they would become part of the critical path. Hence, up to a
point, resources can be taken from noncritical path tasks to shorten tasks on the critical path.
Using critical path analysis, managers can move resources among tasks so as to compress the
schedule.

Answer to Question 2

A




2125004343

  • Member
  • Posts: 566
Reply 2 on: Jul 7, 2018
YES! Correct, THANKS for helping me on my review


tranoy

  • Member
  • Posts: 344
Reply 3 on: Yesterday
Excellent

 

Did you know?

Sperm cells are so tiny that 400 to 500 million (400,000,000–500,000,000) of them fit onto 1 tsp.

Did you know?

About 600,000 particles of skin are shed every hour by each human. If you live to age 70 years, you have shed 105 pounds of dead skin.

Did you know?

Asthma-like symptoms were first recorded about 3,500 years ago in Egypt. The first manuscript specifically written about asthma was in the year 1190, describing a condition characterized by sudden breathlessness. The treatments listed in this manuscript include chicken soup, herbs, and sexual abstinence.

Did you know?

This year, an estimated 1.4 million Americans will have a new or recurrent heart attack.

Did you know?

Vampire bats have a natural anticoagulant in their saliva that permits continuous bleeding after they painlessly open a wound with their incisors. This capillary blood does not cause any significant blood loss to their victims.

For a complete list of videos, visit our video library