Author Question: Changes to the baseline project plan might be motivated by: A) a slipped completion date of an ... (Read 27 times)

mp14

  • Hero Member
  • *****
  • Posts: 534
Changes to the baseline project plan might be motivated by:
 
  A) a slipped completion date of an activity.
  B) a bungled activity that must be redone.
  C) the identification of a new activity that becomes evident later in the project.
  D) an unforeseen change in personnel due to sickness, resignation, or termination.
  E) all of the above.

Question 2

A Web site's customer is represented as a source on a data-flow diagram.
 
  Indicate whether the statement is true or false



bfulkerson77

  • Sr. Member
  • ****
  • Posts: 331
Answer to Question 1

E
Explanation: E) Missed completion dates, scope creep, personnel changes and redoing an activity can cause a change to the completion date.

Answer to Question 2

TRUE
Explanation: A customer is a source on a DFD, represented by a square, and considered outside the system.
CL



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The Romans did not use numerals to indicate fractions but instead used words to indicate parts of a whole.

Did you know?

The most common childhood diseases include croup, chickenpox, ear infections, flu, pneumonia, ringworm, respiratory syncytial virus, scabies, head lice, and asthma.

Did you know?

There are 20 feet of blood vessels in each square inch of human skin.

Did you know?

The newest statin drug, rosuvastatin, has been called a superstatin because it appears to reduce LDL cholesterol to a greater degree than the other approved statin drugs.

Did you know?

When taking monoamine oxidase inhibitors, people should avoid a variety of foods, which include alcoholic beverages, bean curd, broad (fava) bean pods, cheese, fish, ginseng, protein extracts, meat, sauerkraut, shrimp paste, soups, and yeast.

For a complete list of videos, visit our video library