Author Question: Changes to the baseline project plan might be motivated by: A) a slipped completion date of an ... (Read 60 times)

mp14

  • Hero Member
  • *****
  • Posts: 534
Changes to the baseline project plan might be motivated by:
 
  A) a slipped completion date of an activity.
  B) a bungled activity that must be redone.
  C) the identification of a new activity that becomes evident later in the project.
  D) an unforeseen change in personnel due to sickness, resignation, or termination.
  E) all of the above.

Question 2

A Web site's customer is represented as a source on a data-flow diagram.
 
  Indicate whether the statement is true or false



bfulkerson77

  • Sr. Member
  • ****
  • Posts: 331
Answer to Question 1

E
Explanation: E) Missed completion dates, scope creep, personnel changes and redoing an activity can cause a change to the completion date.

Answer to Question 2

TRUE
Explanation: A customer is a source on a DFD, represented by a square, and considered outside the system.
CL



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

On average, someone in the United States has a stroke about every 40 seconds. This is about 795,000 people per year.

Did you know?

Urine turns bright yellow if larger than normal amounts of certain substances are consumed; one of these substances is asparagus.

Did you know?

Hyperthyroidism leads to an increased rate of metabolism and affects about 1% of women but only 0.1% of men. For most people, this increased metabolic rate causes the thyroid gland to become enlarged (known as a goiter).

Did you know?

Women are 50% to 75% more likely than men to experience an adverse drug reaction.

Did you know?

One way to reduce acid reflux is to lose two or three pounds. Most people lose weight in the belly area first when they increase exercise, meaning that heartburn can be reduced quickly by this method.

For a complete list of videos, visit our video library