Developing an understanding of the content and complexity of the project is the purpose of:
 
  A) developing a project charter activity of the project planning phase.
  B) setting a baseline project plan activity of the project planning phase.
  C) determining project standards and procedures activity of the project planning phase.
  D) describing the project scope, alternatives, and feasibility activity of the project planning phase.
  E) closing down the project activity of the project planning phase.

Question 2

Which of the following is NOT a true statement regarding project planning?
 
  A) Project planning often requires that you make numerous assumptions about resource availability and potential problems.
  B) Project planning is the second phase of the project management process.
  C) Project planning focuses on defining clear, discrete activities and the work needed to complete each activity within a single project.
  D) The repetitive nature of the project management process requires that plans be constantly monitored throughout the project and periodically updated.
  E) Monitoring project progress against the baseline project plan is the first project planning activity.


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Jmfn03

  • Sr. Member
  • ****
  • Posts: 323
Lorsum iprem. Lorsus sur ipci. Lorsem sur iprem. Lorsum sur ipdi, lorsem sur ipci. Lorsum sur iprium, valum sur ipci et, vala sur ipci. Lorsem sur ipci, lorsa sur iprem. Valus sur ipdi. Lorsus sur iprium nunc, valem sur iprium. Valem sur ipdi. Lorsa sur iprium. Lorsum sur iprium. Valem sur ipdi. Vala sur ipdi nunc, valem sur ipdi, valum sur ipdi, lorsem sur ipdi, vala sur ipdi. Valem sur iprem nunc, lorsa sur iprium. Valum sur ipdi et, lorsus sur ipci. Valem sur iprem. Valem sur ipci. Lorsa sur iprium. Lorsem sur ipci, valus sur iprem. Lorsem sur iprem nunc, valus sur iprium.
Answer Preview
Only 45% of students answer this correctly




altibaby

  • Member
  • Posts: 562
Reply 2 on: Jul 7, 2018
Thanks for the timely response, appreciate it


bassamabas

  • Member
  • Posts: 294
Reply 3 on: Yesterday
Great answer, keep it coming :)

 

Did you know?

Asthma cases in Americans are about 75% higher today than they were in 1980.

Did you know?

Patients who cannot swallow may receive nutrition via a parenteral route—usually, a catheter is inserted through the chest into a large vein going into the heart.

Did you know?

Drying your hands with a paper towel will reduce the bacterial count on your hands by 45–60%.

Did you know?

Approximately one in three babies in the United States is now delivered by cesarean section. The number of cesarean sections in the United States has risen 46% since 1996.

Did you know?

The top five reasons that children stay home from school are as follows: colds, stomach flu (gastroenteritis), ear infection (otitis media), pink eye (conjunctivitis), and sore throat.

For a complete list of videos, visit our video library