Developing an understanding of the content and complexity of the project is the purpose of:
 
  A) developing a project charter activity of the project planning phase.
  B) setting a baseline project plan activity of the project planning phase.
  C) determining project standards and procedures activity of the project planning phase.
  D) describing the project scope, alternatives, and feasibility activity of the project planning phase.
  E) closing down the project activity of the project planning phase.

Question 2

Which of the following is NOT a true statement regarding project planning?
 
  A) Project planning often requires that you make numerous assumptions about resource availability and potential problems.
  B) Project planning is the second phase of the project management process.
  C) Project planning focuses on defining clear, discrete activities and the work needed to complete each activity within a single project.
  D) The repetitive nature of the project management process requires that plans be constantly monitored throughout the project and periodically updated.
  E) Monitoring project progress against the baseline project plan is the first project planning activity.


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Jmfn03

  • Sr. Member
  • ****
  • Posts: 323
Lorsum iprem. Lorsus sur ipci. Lorsem sur iprem. Lorsum sur ipdi, lorsem sur ipci. Lorsum sur iprium, valum sur ipci et, vala sur ipci. Lorsem sur ipci, lorsa sur iprem. Valus sur ipdi. Lorsus sur iprium nunc, valem sur iprium. Valem sur ipdi. Lorsa sur iprium. Lorsum sur iprium. Valem sur ipdi. Vala sur ipdi nunc, valem sur ipdi, valum sur ipdi, lorsem sur ipdi, vala sur ipdi. Valem sur iprem nunc, lorsa sur iprium. Valum sur ipdi et, lorsus sur ipci. Valem sur iprem. Valem sur ipci. Lorsa sur iprium. Lorsem sur ipci, valus sur iprem. Lorsem sur iprem nunc, valus sur iprium.
Answer Preview
Only 45% of students answer this correctly




altibaby

  • Member
  • Posts: 562
Reply 2 on: Jul 7, 2018
Thanks for the timely response, appreciate it


deja

  • Member
  • Posts: 332
Reply 3 on: Yesterday
Gracias!

 

Did you know?

When blood is deoxygenated and flowing back to the heart through the veins, it is dark reddish-blue in color. Blood in the arteries that is oxygenated and flowing out to the body is bright red. Whereas arterial blood comes out in spurts, venous blood flows.

Did you know?

Persons who overdose with cardiac glycosides have a better chance of overall survival if they can survive the first 24 hours after the overdose.

Did you know?

Lower drug doses for elderly patients should be used first, with titrations of the dose as tolerated to prevent unwanted drug-related pharmacodynamic effects.

Did you know?

Blood is approximately twice as thick as water because of the cells and other components found in it.

Did you know?

Asthma-like symptoms were first recorded about 3,500 years ago in Egypt. The first manuscript specifically written about asthma was in the year 1190, describing a condition characterized by sudden breathlessness. The treatments listed in this manuscript include chicken soup, herbs, and sexual abstinence.

For a complete list of videos, visit our video library