Author Question: Which of the following is not a critical success factor for ERP project success? A) Project ... (Read 67 times)

awywial

  • Hero Member
  • *****
  • Posts: 577
Which of the following is not a critical success factor for ERP project success?
 
  A) Project leaders should have prior experience with large scale systems.
  B) Third party consultants should transfer their knowledge, not just implement.
  C) Top management should be engaged in the project to ensure managerial buy-in.
  D) The ERP system should be customized to match current business processes.

Question 2

A web-based portal allows users to get access to their ERP applications through their browser.
 
  Indicate whether the statement is true or false



tandmlomax84

  • Sr. Member
  • ****
  • Posts: 323
Answer to Question 1

D

Answer to Question 2

TRUE



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

In women, pharmacodynamic differences include increased sensitivity to (and increased effectiveness of) beta-blockers, opioids, selective serotonin reuptake inhibitors, and typical antipsychotics.

Did you know?

Fungal nail infections account for up to 30% of all skin infections. They affect 5% of the general population—mostly people over the age of 70.

Did you know?

About 3.2 billion people, nearly half the world population, are at risk for malaria. In 2015, there are about 214 million malaria cases and an estimated 438,000 malaria deaths.

Did you know?

There are 20 feet of blood vessels in each square inch of human skin.

Did you know?

The shortest mature adult human of whom there is independent evidence was Gul Mohammed in India. In 1990, he was measured in New Delhi and stood 22.5 inches tall.

For a complete list of videos, visit our video library