Author Question: What is the difference between the IRR and the MIRR? What will be an ideal ... (Read 21 times)

audragclark

  • Hero Member
  • *****
  • Posts: 579
What is the difference between the IRR and the MIRR?
 
  What will be an ideal response?

Question 2

Which of the following should NOT be included as investment costs in evaluating a capital asset?
 
  A) installation expenses
  B) shipping expenses
  C) employee training expenses
  D) interest payments and other financing cash flows that result from raising funds to finance a
  project


steff9894

  • Sr. Member
  • ****
  • Posts: 337
Answer to Question 1

The internal rate of return (IRR) attempts to answer the question, What rate of return does this project earn? For
computational purposes, the internal rate of return is defined as the discount rate that equates the present value of the
project's free cash flows with the project's initial cash outlay. It is referred to it as the internal rate of return because it
is dependent solely upon the project's cash flows, not on rates of return or the opportunity cost of money.
The modified internal rate of return (MIRR), has gained popularity as an alternative to the IRR method because it
avoids multiple IRRs and allows the decision maker to directly specify the appropriate reinvestment rate. As a result,
the MIRR provides the decision maker with the intuitive appeal of the IRR coupled with a reinvestment rate
assumption that prevents the possibility of multiple rates of return. Is the reinvestment rate assumption really a
problem? The answer is yes. One of the problems of the IRR is that it creates unrealistic expectations for both the
corporation and its shareholders.
There is more than one way to compute the MIRR, and each method can potentially result in a different value for the
MIRR. We used what we consider to be the most common way to compute the MIRR, which is also the one used by
Excel. Specifically, we discounted the project's negative cash flows back to the present using the project's required rate
of return and then compounded all the positive cash flows to the end of the project's life at the required rate of return
before computing the MIRR. Some analysts compute the MIRR by discounting negative cash flows back to the present
using the project's required rate of return and then computing the MIRR. Neither method is necessarily better than the
other.

Answer to Question 2

D



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

audragclark

  • Hero Member
  • *****
  • Posts: 579

steff9894

  • Sr. Member
  • ****
  • Posts: 337

 

Did you know?

It is widely believed that giving a daily oral dose of aspirin to heart attack patients improves their chances of survival because the aspirin blocks the formation of new blood clots.

Did you know?

There can actually be a 25-hour time difference between certain locations in the world. The International Date Line passes between the islands of Samoa and American Samoa. It is not a straight line, but "zig-zags" around various island chains. Therefore, Samoa and nearby islands have one date, while American Samoa and nearby islands are one day behind. Daylight saving time is used in some islands, but not in others—further shifting the hours out of sync with natural time.

Did you know?

Patients who have undergone chemotherapy for the treatment of cancer often complain of a lack of mental focus; memory loss; and a general diminution in abilities such as multitasking, attention span, and general mental agility.

Did you know?

Every 10 seconds, a person in the United States goes to the emergency room complaining of head pain. About 1.2 million visits are for acute migraine attacks.

Did you know?

In most cases, kidneys can recover from almost complete loss of function, such as in acute kidney (renal) failure.

For a complete list of videos, visit our video library