Author Question: The _____ is a project management tool that illustrates the relationships among all the activities ... (Read 56 times)

a0266361136

  • Hero Member
  • *****
  • Posts: 538
The _____ is a project management tool that illustrates the relationships among all the activities involved in completing a project and identifies the sequence of activities likely to take the longest to complete.
 A) critical path method
  B) Gantt chart
  C) program evaluation and review technique
  D) vertical integration technique

Question 2

Which of the following is a disadvantage of holding larger inventories?
 A) Increased ordering costs
  B) Increased risk of stock-outs and lost sales
  C) Additional holding costs
  D) Irregular production schedules



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

joanwhite

  • Sr. Member
  • ****
  • Posts: 308
Answer to Question 1

A

Answer to Question 2

C





 

Did you know?

Approximately 15–25% of recognized pregnancies end in miscarriage. However, many miscarriages often occur before a woman even knows she is pregnant.

Did you know?

Illness; diuretics; laxative abuse; hot weather; exercise; sweating; caffeine; alcoholic beverages; starvation diets; inadequate carbohydrate consumption; and diets high in protein, salt, or fiber can cause people to become dehydrated.

Did you know?

Most women experience menopause in their 50s. However, in 1994, an Italian woman gave birth to a baby boy when she was 61 years old.

Did you know?

Blood is approximately twice as thick as water because of the cells and other components found in it.

Did you know?

When blood is exposed to air, it clots. Heparin allows the blood to come in direct contact with air without clotting.

For a complete list of videos, visit our video library