Author Question: What are some of the inherent advantages and disadvantages in measuring project duration in calendar ... (Read 35 times)

newbem

  • Hero Member
  • *****
  • Posts: 579
What are some of the inherent advantages and disadvantages in measuring project duration in calendar days? Working days?
 
  What will be an ideal response?

Question 2

What are the primary grounds on which the contractor can typically terminate the contract?
 
  What will be an ideal response?



bd5255

  • Sr. Member
  • ****
  • Posts: 386
Answer to Question 1

Where calendar days are concerned, the strongest inherent advantage is that
there is little chance of confusion as the definition of calendar is essentially universal.
Where contractors are concerned, calendar days may pose a disadvantage when weather
precludes the accomplishment of work. Owners may be reluctant to grant time
extensions.

An inherent disadvantage of using working days is that the definition of working days
can vary. It must be clearly defined in the contract or a dispute may readily occur. Some
owners will count all days that are worked as working days. This can playa hardship on a
contractor if an attempt is made to make up time or to get ahead of schedule. Any
weekends that are then worked will be counted as working days. An advantage of
scheduling with working days, especially for the contractor, is that there tends to be a
fairer allocation of time for project performance.

Answer to Question 2

The contractor can terminate a contract when the owner fails to make payments
to the contractor that have been earned and are due. This is the only universal reason for
which the contractor can terminate the contract. Another reason for termination by the
contractor would include a condition whereby the construction effort is stopped for a
stipulated period of time by a court or other public authority.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

newbem

  • Hero Member
  • *****
  • Posts: 579
Both answers were spot on, thank you once again




 

Did you know?

Acute bronchitis is an inflammation of the breathing tubes (bronchi), which causes increased mucus production and other changes. It is usually caused by bacteria or viruses, can be serious in people who have pulmonary or cardiac diseases, and can lead to pneumonia.

Did you know?

Medication errors are more common among seriously ill patients than with those with minor conditions.

Did you know?

To maintain good kidney function, you should drink at least 3 quarts of water daily. Water dilutes urine and helps prevent concentrations of salts and minerals that can lead to kidney stone formation. Chronic dehydration is a major contributor to the development of kidney stones.

Did you know?

Cucumber slices relieve headaches by tightening blood vessels, reducing blood flow to the area, and relieving pressure.

Did you know?

People who have myopia, or nearsightedness, are not able to see objects at a distance but only up close. It occurs when the cornea is either curved too steeply, the eye is too long, or both. This condition is progressive and worsens with time. More than 100 million people in the United States are nearsighted, but only 20% of those are born with the condition. Diet, eye exercise, drug therapy, and corrective lenses can all help manage nearsightedness.

For a complete list of videos, visit our video library