Author Question: In engineering contracts, what is a typical format for payments to the engineering firm for design ... (Read 321 times)

Chloeellawright

  • Hero Member
  • *****
  • Posts: 588
In engineering contracts, what is a typical format for payments to the engineering firm for design services?
 
  What will be an ideal response?

Question 2

Submittal of bonds and insurance certificates should be submitted by the bidder to whom the contract has been awarded:
 
  A. at the time of submitting the original Bid.
   B. after receiving the Notice to Proceed from the owner/engineer.
   C. after receiving the Notice to Proceed, but before signing the Agreement.
   D. after receiving Notice of Award, but before owner signs the Agreement.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Chelseyj.hasty

  • Sr. Member
  • ****
  • Posts: 319
Answer to Question 1

For engineering contracts the typical format for payments to engineering firms for design services is the following:

a) 10 preliminary investigation
b) 35 preliminary design
c) 65 final design unchecked
d) 100 final design and checked

Answer to Question 2

D



Chloeellawright

  • Hero Member
  • *****
  • Posts: 588
Both answers were spot on, thank you once again




 

Did you know?

Blood in the urine can be a sign of a kidney stone, glomerulonephritis, or other kidney problems.

Did you know?

Asthma is the most common chronic childhood disease in the world. Most children who develop asthma have symptoms before they are 5 years old.

Did you know?

Before a vaccine is licensed in the USA, the Food and Drug Administration (FDA) reviews it for safety and effectiveness. The CDC then reviews all studies again, as well as the American Academy of Pediatrics and the American Academy of Family Physicians. Every lot of vaccine is tested before administration to the public, and the FDA regularly inspects vaccine manufacturers' facilities.

Did you know?

Patients who cannot swallow may receive nutrition via a parenteral route—usually, a catheter is inserted through the chest into a large vein going into the heart.

Did you know?

Side effects from substance abuse include nausea, dehydration, reduced productivitiy, and dependence. Though these effects usually worsen over time, the constant need for the substance often overcomes rational thinking.

For a complete list of videos, visit our video library