Author Question: For an activity with more than one immediate predecessor activity, which of the following is used to ... (Read 65 times)

Yolanda

  • Hero Member
  • *****
  • Posts: 757
For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish (EF) time?
 a. the largest EF among the immediate predecessors.
  b. the average EF among the immediate predecessors.
  c. the largest LF among the immediate predecessors.
  d. the difference in EF among the immediate predecessors.

Question 2

The interval estimate of the mean value of y for a given value of x is the _____.
 a. confidence interval
  b. prediction interval
  c. residual interval
  d. correlation interval



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

leahchrapun

  • Sr. Member
  • ****
  • Posts: 332
Answer to Question 1

A

Answer to Question 2

a




Yolanda

  • Member
  • Posts: 757
Reply 2 on: Jun 24, 2018
Gracias!


ashely1112

  • Member
  • Posts: 347
Reply 3 on: Yesterday
Great answer, keep it coming :)

 

Did you know?

The first war in which wide-scale use of anesthetics occurred was the Civil War, and 80% of all wounds were in the extremities.

Did you know?

Alzheimer's disease affects only about 10% of people older than 65 years of age. Most forms of decreased mental function and dementia are caused by disuse (letting the mind get lazy).

Did you know?

In 2010, opiate painkllers, such as morphine, OxyContin®, and Vicodin®, were tied to almost 60% of drug overdose deaths.

Did you know?

Addicts to opiates often avoid treatment because they are afraid of withdrawal. Though unpleasant, with proper management, withdrawal is rarely fatal and passes relatively quickly.

Did you know?

There are more nerve cells in one human brain than there are stars in the Milky Way.

For a complete list of videos, visit our video library