Author Question: When activity times are uncertain, a. assume they are normally distributed. b. calculate the ... (Read 94 times)

michelleunicorn

  • Hero Member
  • *****
  • Posts: 565
When activity times are uncertain,
 a. assume they are normally distributed.
  b. calculate the expected time, using (a + 4m + b)/6.
  c. use the most likely time.
  d. calculate the expected time, using (a + m + b)/3.

Question 2

In a residual plot against x that does NOT suggest we should challenge the assumptions of our regression model, we would expect to see a _____.
 a. horizontal band of points centered near 0
  b. widening band of points
  c. band of points having a slope consistent with that of the regression equation
  d. parabolic band of points



brbarasa

  • Sr. Member
  • ****
  • Posts: 308
Answer to Question 1

B

Answer to Question 2

a



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Drugs are in development that may cure asthma and hay fever once and for all. They target leukotrienes, which are known to cause tightening of the air passages in the lungs and increase mucus productions in nasal passages.

Did you know?

Drug-induced pharmacodynamic effects manifested in older adults include drug-induced renal toxicity, which can be a major factor when these adults are experiencing other kidney problems.

Did you know?

Approximately 70% of expectant mothers report experiencing some symptoms of morning sickness during the first trimester of pregnancy.

Did you know?

Certain topical medications such as clotrimazole and betamethasone are not approved for use in children younger than 12 years of age. They must be used very cautiously, as directed by a doctor, to treat any child. Children have a much greater response to topical steroid medications.

Did you know?

Excessive alcohol use costs the country approximately $235 billion every year.

For a complete list of videos, visit our video library