Author Question: When activity times are uncertain, a. assume they are normally distributed. b. calculate the ... (Read 107 times)

michelleunicorn

  • Hero Member
  • *****
  • Posts: 565
When activity times are uncertain,
 a. assume they are normally distributed.
  b. calculate the expected time, using (a + 4m + b)/6.
  c. use the most likely time.
  d. calculate the expected time, using (a + m + b)/3.

Question 2

In a residual plot against x that does NOT suggest we should challenge the assumptions of our regression model, we would expect to see a _____.
 a. horizontal band of points centered near 0
  b. widening band of points
  c. band of points having a slope consistent with that of the regression equation
  d. parabolic band of points



brbarasa

  • Sr. Member
  • ****
  • Posts: 308
Answer to Question 1

B

Answer to Question 2

a



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

For high blood pressure (hypertension), a new class of drug, called a vasopeptidase blocker (inhibitor), has been developed. It decreases blood pressure by simultaneously dilating the peripheral arteries and increasing the body's loss of salt.

Did you know?

More than 4.4billion prescriptions were dispensed within the United States in 2016.

Did you know?

There are more sensory neurons in the tongue than in any other part of the body.

Did you know?

In 2010, opiate painkllers, such as morphine, OxyContin®, and Vicodin®, were tied to almost 60% of drug overdose deaths.

Did you know?

When intravenous medications are involved in adverse drug events, their harmful effects may occur more rapidly, and be more severe than errors with oral medications. This is due to the direct administration into the bloodstream.

For a complete list of videos, visit our video library