Author Question: Arcs in a project network indicate a. completion times. b. precedence relationships. c. ... (Read 138 times)

nenivikky

  • Hero Member
  • *****
  • Posts: 516
Arcs in a project network indicate
 a. completion times.
  b. precedence relationships.
  c. activities.
  d. the critical path.

Question 2

An ANOVA procedure is used for data obtained from four populations. Four samples, each comprised of 30 observations, were taken from the four populations. The numerator and denominator (respectively) degrees of freedom for the critical value of F are _____.
 a. 3 and 30
  b. 4 and 30
  c. 3 and 119
  d. 3 and 116



C.mcnichol98

  • Sr. Member
  • ****
  • Posts: 314
Answer to Question 1

B

Answer to Question 2

d



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

If you could remove all of your skin, it would weigh up to 5 pounds.

Did you know?

Alzheimer's disease affects only about 10% of people older than 65 years of age. Most forms of decreased mental function and dementia are caused by disuse (letting the mind get lazy).

Did you know?

A serious new warning has been established for pregnant women against taking ACE inhibitors during pregnancy. In the study, the risk of major birth defects in children whose mothers took ACE inhibitors during the first trimester was nearly three times higher than in children whose mothers didn't take ACE inhibitors. Physicians can prescribe alternative medications for pregnant women who have symptoms of high blood pressure.

Did you know?

Street names for barbiturates include reds, red devils, yellow jackets, blue heavens, Christmas trees, and rainbows. They are commonly referred to as downers.

Did you know?

The first oral chemotherapy drug for colon cancer was approved by FDA in 2001.

For a complete list of videos, visit our video library