Author Question: Construction on a building began on January 2, 2015. As between a construction mortgage recorded on ... (Read 92 times)

cnetterville

  • Hero Member
  • *****
  • Posts: 547
Construction on a building began on January 2, 2015. As between a construction mortgage recorded on January 11, 2015, and a plumber who records a lien on March 15, 2015:
 A) The plumber will have priority in a dates back state.
 B) The construction mortgage always has priority.
 C) The plumber will have priority if it did its work prior to January 11.
 D) The plumber and construction mortgage are on equal footing.

Question 2

A transfer of property by a debtor within ______ prior to filing with the intent to hinder, delay, or defraud creditors is called a(n) ______.
 A) 3 months, proof of claim.
 B) 3 months, voidable preference
 C) 12 months, proof of claim
 D) 12 months, voidable preference.



mceravolo

  • Sr. Member
  • ****
  • Posts: 349
Answer to Question 1

A

Answer to Question 2

D



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Between 1999 and 2012, American adults with high total cholesterol decreased from 18.3% to 12.9%

Did you know?

You should not take more than 1,000 mg of vitamin E per day. Doses above this amount increase the risk of bleeding problems that can lead to a stroke.

Did you know?

When taking monoamine oxidase inhibitors, people should avoid a variety of foods, which include alcoholic beverages, bean curd, broad (fava) bean pods, cheese, fish, ginseng, protein extracts, meat, sauerkraut, shrimp paste, soups, and yeast.

Did you know?

Patients who cannot swallow may receive nutrition via a parenteral route—usually, a catheter is inserted through the chest into a large vein going into the heart.

Did you know?

During pregnancy, a woman is more likely to experience bleeding gums and nosebleeds caused by hormonal changes that increase blood flow to the mouth and nose.

For a complete list of videos, visit our video library