Author Question: In a PERT network, a/an _____ is the earliest time a project can finish given the expected activity ... (Read 40 times)

fnuegbu

  • Hero Member
  • *****
  • Posts: 539
In a PERT network, a/an _____ is the earliest time a project can finish given the expected activity time.
 a. late finish
 b. on time start
 c. on time finish
  d. early start
 e. early finish

Question 2

According to the financial approach, choosing a channel structure is analogous to:
 a. Aspinwall's parallel systems approach.
  b. An investment decision of capital budgeting.
  c. Most of the management science approaches.
  d. The Bayesian approach to channel choice.
  e. Simulations of channel choice decisions.



Viet Thy

  • Sr. Member
  • ****
  • Posts: 329
Answer to Question 1

e

Answer to Question 2

B



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Acute bronchitis is an inflammation of the breathing tubes (bronchi), which causes increased mucus production and other changes. It is usually caused by bacteria or viruses, can be serious in people who have pulmonary or cardiac diseases, and can lead to pneumonia.

Did you know?

Complications of influenza include: bacterial pneumonia, ear and sinus infections, dehydration, and worsening of chronic conditions such as asthma, congestive heart failure, or diabetes.

Did you know?

Intradermal injections are somewhat difficult to correctly administer because the skin layers are so thin that it is easy to accidentally punch through to the deeper subcutaneous layer.

Did you know?

According to research, pregnant women tend to eat more if carrying a baby boy. Male fetuses may secrete a chemical that stimulates their mothers to step up her energy intake.

Did you know?

There used to be a metric calendar, as well as metric clocks. The metric calendar, or "French Republican Calendar" divided the year into 12 months, but each month was divided into three 10-day weeks. Each day had 10 decimal hours. Each hour had 100 decimal minutes. Due to lack of popularity, the metric clocks and calendars were ended in 1795, three years after they had been first marketed.

For a complete list of videos, visit our video library