Author Question: What is a critical path? How is a critical path analysis done? What will be an ideal ... (Read 142 times)

2125004343

  • Hero Member
  • *****
  • Posts: 566
What is a critical path? How is a critical path analysis done?
 
  What will be an ideal response?

Question 2

In RFM analysis, an R score of 5 shows that ________.
 
  A) a customer has not made any recent purchases
  B) a customer has bought the most expensive items
  C) a customer has frequently ordered expensive items
  D) a customer has purchased the least expensive items



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

karlss

  • Sr. Member
  • ****
  • Posts: 321
Answer to Question 1

A critical path is a sequence of activities that determine the earliest date by which a
project can be completed. The earliest date is the date determined by considering the longest path
through the network of activities. Paying attention to task dependencies, a planner can compress
tasks as much as possible. Those tasks that cannot be further compressed lie on the critical path.
Microsoft Project and other project-planning applications can readily identify critical path tasks.
Managers can use the critical path to perform critical path analysis. If a task is on the critical
path, and if that task runs late, the project will be late. Hence, tasks on the critical path cannot be
allowed to run late if the project is to be delivered on time. Additionally, tasks not on the critical
path can run late to the point at which they would become part of the critical path. Hence, up to a
point, resources can be taken from noncritical path tasks to shorten tasks on the critical path.
Using critical path analysis, managers can move resources among tasks so as to compress the
schedule.

Answer to Question 2

A




2125004343

  • Member
  • Posts: 566
Reply 2 on: Jul 7, 2018
Thanks for the timely response, appreciate it


abro1885

  • Member
  • Posts: 337
Reply 3 on: Yesterday
Great answer, keep it coming :)

 

Did you know?

Serum cholesterol testing in adults is recommended every 1 to 5 years. People with diabetes and a family history of high cholesterol should be tested even more frequently.

Did you know?

Many supplement containers do not even contain what their labels say. There are many documented reports of products containing much less, or more, that what is listed on their labels. They may also contain undisclosed prescription drugs and even contaminants.

Did you know?

The human body produces and destroys 15 million blood cells every second.

Did you know?

The Food and Drug Administration has approved Risperdal, an adult antipsychotic drug, for the symptomatic treatment of irritability in children and adolescents with autism. The approval is the first for the use of a drug to treat behaviors associated with autism in children. These behaviors are included under the general heading of irritability and include aggression, deliberate self-injury, and temper tantrums.

Did you know?

There used to be a metric calendar, as well as metric clocks. The metric calendar, or "French Republican Calendar" divided the year into 12 months, but each month was divided into three 10-day weeks. Each day had 10 decimal hours. Each hour had 100 decimal minutes. Due to lack of popularity, the metric clocks and calendars were ended in 1795, three years after they had been first marketed.

For a complete list of videos, visit our video library