Author Question: What is a critical path? How is a critical path analysis done? What will be an ideal ... (Read 109 times)

2125004343

  • Hero Member
  • *****
  • Posts: 566
What is a critical path? How is a critical path analysis done?
 
  What will be an ideal response?

Question 2

In RFM analysis, an R score of 5 shows that ________.
 
  A) a customer has not made any recent purchases
  B) a customer has bought the most expensive items
  C) a customer has frequently ordered expensive items
  D) a customer has purchased the least expensive items



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

karlss

  • Sr. Member
  • ****
  • Posts: 321
Answer to Question 1

A critical path is a sequence of activities that determine the earliest date by which a
project can be completed. The earliest date is the date determined by considering the longest path
through the network of activities. Paying attention to task dependencies, a planner can compress
tasks as much as possible. Those tasks that cannot be further compressed lie on the critical path.
Microsoft Project and other project-planning applications can readily identify critical path tasks.
Managers can use the critical path to perform critical path analysis. If a task is on the critical
path, and if that task runs late, the project will be late. Hence, tasks on the critical path cannot be
allowed to run late if the project is to be delivered on time. Additionally, tasks not on the critical
path can run late to the point at which they would become part of the critical path. Hence, up to a
point, resources can be taken from noncritical path tasks to shorten tasks on the critical path.
Using critical path analysis, managers can move resources among tasks so as to compress the
schedule.

Answer to Question 2

A




2125004343

  • Member
  • Posts: 566
Reply 2 on: Jul 7, 2018
Wow, this really help


nanny

  • Member
  • Posts: 313
Reply 3 on: Yesterday
Gracias!

 

Did you know?

Though the United States has largely rejected the metric system, it is used for currency, as in 100 pennies = 1 dollar. Previously, the British currency system was used, with measurements such as 12 pence to the shilling, and 20 shillings to the pound.

Did you know?

In the United States, congenital cytomegalovirus causes one child to become disabled almost every hour. CMV is the leading preventable viral cause of development disability in newborns. These disabilities include hearing or vision loss, and cerebral palsy.

Did you know?

Never take aspirin without food because it is likely to irritate your stomach. Never give aspirin to children under age 12. Overdoses of aspirin have the potential to cause deafness.

Did you know?

It is believed that humans initially contracted crabs from gorillas about 3 million years ago from either sleeping in gorilla nests or eating the apes.

Did you know?

Acute bronchitis is an inflammation of the breathing tubes (bronchi), which causes increased mucus production and other changes. It is usually caused by bacteria or viruses, can be serious in people who have pulmonary or cardiac diseases, and can lead to pneumonia.

For a complete list of videos, visit our video library