This topic contains a solution. Click here to go to the answer

Author Question: What is a critical path? How is a critical path analysis done? What will be an ideal ... (Read 60 times)

2125004343

  • Hero Member
  • *****
  • Posts: 566
What is a critical path? How is a critical path analysis done?
 
  What will be an ideal response?

Question 2

In RFM analysis, an R score of 5 shows that ________.
 
  A) a customer has not made any recent purchases
  B) a customer has bought the most expensive items
  C) a customer has frequently ordered expensive items
  D) a customer has purchased the least expensive items



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

karlss

  • Sr. Member
  • ****
  • Posts: 321
Answer to Question 1

A critical path is a sequence of activities that determine the earliest date by which a
project can be completed. The earliest date is the date determined by considering the longest path
through the network of activities. Paying attention to task dependencies, a planner can compress
tasks as much as possible. Those tasks that cannot be further compressed lie on the critical path.
Microsoft Project and other project-planning applications can readily identify critical path tasks.
Managers can use the critical path to perform critical path analysis. If a task is on the critical
path, and if that task runs late, the project will be late. Hence, tasks on the critical path cannot be
allowed to run late if the project is to be delivered on time. Additionally, tasks not on the critical
path can run late to the point at which they would become part of the critical path. Hence, up to a
point, resources can be taken from noncritical path tasks to shorten tasks on the critical path.
Using critical path analysis, managers can move resources among tasks so as to compress the
schedule.

Answer to Question 2

A




2125004343

  • Member
  • Posts: 566
Reply 2 on: Jul 7, 2018
YES! Correct, THANKS for helping me on my review


duy1981999

  • Member
  • Posts: 341
Reply 3 on: Yesterday
Gracias!

 

Did you know?

Most strokes are caused when blood clots move to a blood vessel in the brain and block blood flow to that area. Thrombolytic therapy can be used to dissolve the clot quickly. If given within 3 hours of the first stroke symptoms, this therapy can help limit stroke damage and disability.

Did you know?

About 3% of all pregnant women will give birth to twins, which is an increase in rate of nearly 60% since the early 1980s.

Did you know?

Approximately one in three babies in the United States is now delivered by cesarean section. The number of cesarean sections in the United States has risen 46% since 1996.

Did you know?

The modern decimal position system was the invention of the Hindus (around 800 AD), involving the placing of numerals to indicate their value (units, tens, hundreds, and so on).

Did you know?

Vampire bats have a natural anticoagulant in their saliva that permits continuous bleeding after they painlessly open a wound with their incisors. This capillary blood does not cause any significant blood loss to their victims.

For a complete list of videos, visit our video library