Author Question: When choosing a weighted system to determine project viability, what should the organization keep in ... (Read 216 times)

pragya sharda

  • Hero Member
  • *****
  • Posts: 566
When choosing a weighted system to determine project viability, what should the organization keep in mind?
 
  A) All requirements should be weighted equally.
  B) Weights are subjective.
  C) The total points have to equal 100.
  D) Requirements and constraints have equal weights.

Question 2

A ________ is the origin and/or destination of the data, and these are sometimes referred to as external entities because they are outside the system.
 
  A) Data graph
  B) Data flow
  C) Process
  D) Source



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

jasonq

  • Sr. Member
  • ****
  • Posts: 335
Answer to Question 1

B

Answer to Question 2

D





 

Did you know?

According to research, pregnant women tend to eat more if carrying a baby boy. Male fetuses may secrete a chemical that stimulates their mothers to step up her energy intake.

Did you know?

During the twentieth century, a variant of the metric system was used in Russia and France in which the base unit of mass was the tonne. Instead of kilograms, this system used millitonnes (mt).

Did you know?

Patients should never assume they are being given the appropriate drugs. They should make sure they know which drugs are being prescribed, and always double-check that the drugs received match the prescription.

Did you know?

Bacteria have flourished on the earth for over three billion years. They were the first life forms on the planet.

Did you know?

The first documented use of surgical anesthesia in the United States was in Connecticut in 1844.

For a complete list of videos, visit our video library