Author Question: When choosing a weighted system to determine project viability, what should the organization keep in ... (Read 212 times)

pragya sharda

  • Hero Member
  • *****
  • Posts: 566
When choosing a weighted system to determine project viability, what should the organization keep in mind?
 
  A) All requirements should be weighted equally.
  B) Weights are subjective.
  C) The total points have to equal 100.
  D) Requirements and constraints have equal weights.

Question 2

A ________ is the origin and/or destination of the data, and these are sometimes referred to as external entities because they are outside the system.
 
  A) Data graph
  B) Data flow
  C) Process
  D) Source



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

jasonq

  • Sr. Member
  • ****
  • Posts: 335
Answer to Question 1

B

Answer to Question 2

D





 

Did you know?

The senior population grows every year. Seniors older than 65 years of age now comprise more than 13% of the total population. However, women outlive men. In the 85-and-over age group, there are only 45 men to every 100 women.

Did you know?

The heart is located in the center of the chest, with part of it tipped slightly so that it taps against the left side of the chest.

Did you know?

More than nineteen million Americans carry the factor V gene that causes blood clots, pulmonary embolism, and heart disease.

Did you know?

When blood is exposed to air, it clots. Heparin allows the blood to come in direct contact with air without clotting.

Did you know?

The average older adult in the United States takes five prescription drugs per day. Half of these drugs contain a sedative. Alcohol should therefore be avoided by most senior citizens because of the dangerous interactions between alcohol and sedatives.

For a complete list of videos, visit our video library