Which of the following refers to the time in which an activity can be completed without delaying the project?
 
  A) Latest expected completion time
  B) Earliest expected completion time
  C) Delay time
  D) End time
  E) Critical time

Question 2

The decomposition of Process 2.4.3.4 would be shown on a level-4 diagram.
 
  Indicate whether the statement is true or false



Bison

  • Sr. Member
  • ****
  • Posts: 342
Answer to Question 1

A
Explanation: A) The latest expected completion time tells us what the very latest time is for an activity to be completed before the project is delayed. This applies to activities along the critical path.

Answer to Question 2

FALSE
Explanation: The decomposition of Process 2.4.3.4 would be shown on a level-3 diagram.
CL



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

People with alcoholism are at a much greater risk of malnutrition than are other people and usually exhibit low levels of most vitamins (especially folic acid). This is because alcohol often takes the place of 50% of their daily intake of calories, with little nutritional value contained in it.

Did you know?

Nearly 31 million adults in America have a total cholesterol level that is more than 240 mg per dL.

Did you know?

A seasonal flu vaccine is the best way to reduce the chances you will get seasonal influenza and spread it to others.

Did you know?

About 3% of all pregnant women will give birth to twins, which is an increase in rate of nearly 60% since the early 1980s.

Did you know?

Adults are resistant to the bacterium that causes Botulism. These bacteria thrive in honey – therefore, honey should never be given to infants since their immune systems are not yet resistant.

For a complete list of videos, visit our video library