Author Question: Optimistic time refers to: A) the maximum period of time for an activity to be completed. B) ... (Read 115 times)

tingc95

  • Hero Member
  • *****
  • Posts: 556
Optimistic time refers to:
 
  A) the maximum period of time for an activity to be completed.
  B) the minimum period of time for an activity to be completed.
  C) the planner's best guess of the amount of time the activity actually will require for completion.
  D) the maximum period of time for an entire project to be completed.
  E) the average period of time for an activity to be completed.

Question 2

Analyzing an organization's activities to determine where value is added to products and/or services and the costs incurred best describes:
 
  A) affinity clustering.
  B) business process reengineering.
  C) value chain analysis.
  D) resource availability.
  E) technical difficulty.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Galvarado142

  • Sr. Member
  • ****
  • Posts: 348
Answer to Question 1

B
Explanation: B) The minimum time that it takes for an activity to be completed is optimistic time.

Answer to Question 2

C
Explanation: C) Value chain analysis involves the extent to which activities add value and costs when developing products and/or services; information systems projects providing the greatest overall benefits will be given priority over those with fewer benefits.
CL




tingc95

  • Member
  • Posts: 556
Reply 2 on: Jul 7, 2018
Wow, this really help


phuda

  • Member
  • Posts: 348
Reply 3 on: Yesterday
:D TYSM

 

Did you know?

When Gabriel Fahrenheit invented the first mercury thermometer, he called "zero degrees" the lowest temperature he was able to attain with a mixture of ice and salt. For the upper point of his scale, he used 96°, which he measured as normal human body temperature (we know it to be 98.6° today because of more accurate thermometers).

Did you know?

The training of an anesthesiologist typically requires four years of college, 4 years of medical school, 1 year of internship, and 3 years of residency.

Did you know?

Human kidneys will clean about 1 million gallons of blood in an average lifetime.

Did you know?

Elderly adults are at greatest risk of stroke and myocardial infarction and have the most to gain from prophylaxis. Patients ages 60 to 80 years with blood pressures above 160/90 mm Hg should benefit from antihypertensive treatment.

Did you know?

There are major differences in the metabolism of morphine and the illegal drug heroin. Morphine mostly produces its CNS effects through m-receptors, and at k- and d-receptors. Heroin has a slight affinity for opiate receptors. Most of its actions are due to metabolism to active metabolites (6-acetylmorphine, morphine, and morphine-6-glucuronide).

For a complete list of videos, visit our video library