Author Question: Optimistic time refers to: A) the maximum period of time for an activity to be completed. B) ... (Read 154 times)

tingc95

  • Hero Member
  • *****
  • Posts: 556
Optimistic time refers to:
 
  A) the maximum period of time for an activity to be completed.
  B) the minimum period of time for an activity to be completed.
  C) the planner's best guess of the amount of time the activity actually will require for completion.
  D) the maximum period of time for an entire project to be completed.
  E) the average period of time for an activity to be completed.

Question 2

Analyzing an organization's activities to determine where value is added to products and/or services and the costs incurred best describes:
 
  A) affinity clustering.
  B) business process reengineering.
  C) value chain analysis.
  D) resource availability.
  E) technical difficulty.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Galvarado142

  • Sr. Member
  • ****
  • Posts: 348
Answer to Question 1

B
Explanation: B) The minimum time that it takes for an activity to be completed is optimistic time.

Answer to Question 2

C
Explanation: C) Value chain analysis involves the extent to which activities add value and costs when developing products and/or services; information systems projects providing the greatest overall benefits will be given priority over those with fewer benefits.
CL




tingc95

  • Member
  • Posts: 556
Reply 2 on: Jul 7, 2018
Excellent


nathang24

  • Member
  • Posts: 314
Reply 3 on: Yesterday
YES! Correct, THANKS for helping me on my review

 

Did you know?

Human neurons are so small that they require a microscope in order to be seen. However, some neurons can be up to 3 feet long, such as those that extend from the spinal cord to the toes.

Did you know?

Human stomach acid is strong enough to dissolve small pieces of metal such as razor blades or staples.

Did you know?

On average, someone in the United States has a stroke about every 40 seconds. This is about 795,000 people per year.

Did you know?

Hippocrates noted that blood separates into four differently colored liquids when removed from the body and examined: a pure red liquid mixed with white liquid material with a yellow-colored froth at the top and a black substance that settles underneath; he named these the four humors (for blood, phlegm, yellow bile, and black bile).

Did you know?

Many supplement containers do not even contain what their labels say. There are many documented reports of products containing much less, or more, that what is listed on their labels. They may also contain undisclosed prescription drugs and even contaminants.

For a complete list of videos, visit our video library