Author Question: The amount of time that an activity can be delayed without delaying the project refers to: A) ... (Read 105 times)

geoffrey

  • Hero Member
  • *****
  • Posts: 880
The amount of time that an activity can be delayed without delaying the project refers to:
 
  A) noncritical time.
  B) slack time.
  C) down time.
  D) delay time.
  E) stop time.

Question 2

An identifier is a candidate key that has been selected as the unique, identifying characteristic for an entity type.
 
  Indicate whether the statement is true or false



amy.lauersdorf90

  • Sr. Member
  • ****
  • Posts: 327
Answer to Question 1

B
Explanation: B) Slack time is the amount of time that an activity can be delayed without causing further delay on the project.

Answer to Question 2

TRUE
Explanation: You can think of a presidential race where several candidates could be nominated (candidate key), but only one is selected (identifier).
CL



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The toxic levels for lithium carbonate are close to the therapeutic levels. Signs of toxicity include fine hand tremor, polyuria, mild thirst, nausea, general discomfort, diarrhea, vomiting, drowsiness, muscular weakness, lack of coordination, ataxia, giddiness, tinnitus, and blurred vision.

Did you know?

More than 150,000 Americans killed by cardiovascular disease are younger than the age of 65 years.

Did you know?

On average, the stomach produces 2 L of hydrochloric acid per day.

Did you know?

More than one-third of adult Americans are obese. Diseases that kill the largest number of people annually, such as heart disease, cancer, diabetes, stroke, and hypertension, can be attributed to diet.

Did you know?

Eating food that has been cooked with poppy seeds may cause you to fail a drug screening test, because the seeds contain enough opiate alkaloids to register as a positive.

For a complete list of videos, visit our video library