Author Question: The amount of time that an activity can be delayed without delaying the project refers to: A) ... (Read 117 times)

geoffrey

  • Hero Member
  • *****
  • Posts: 880
The amount of time that an activity can be delayed without delaying the project refers to:
 
  A) noncritical time.
  B) slack time.
  C) down time.
  D) delay time.
  E) stop time.

Question 2

An identifier is a candidate key that has been selected as the unique, identifying characteristic for an entity type.
 
  Indicate whether the statement is true or false



amy.lauersdorf90

  • Sr. Member
  • ****
  • Posts: 327
Answer to Question 1

B
Explanation: B) Slack time is the amount of time that an activity can be delayed without causing further delay on the project.

Answer to Question 2

TRUE
Explanation: You can think of a presidential race where several candidates could be nominated (candidate key), but only one is selected (identifier).
CL



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Serum cholesterol testing in adults is recommended every 1 to 5 years. People with diabetes and a family history of high cholesterol should be tested even more frequently.

Did you know?

When intravenous medications are involved in adverse drug events, their harmful effects may occur more rapidly, and be more severe than errors with oral medications. This is due to the direct administration into the bloodstream.

Did you know?

The largest baby ever born weighed more than 23 pounds but died just 11 hours after his birth in 1879. The largest surviving baby was born in October 2009 in Sumatra, Indonesia, and weighed an astounding 19.2 pounds at birth.

Did you know?

Medication errors are three times higher among children and infants than with adults.

Did you know?

Elderly adults are living longer, and causes of death are shifting. At the same time, autopsy rates are at or near their lowest in history.

For a complete list of videos, visit our video library