Developing an understanding of the content and complexity of the project is the purpose of:
 
  A) developing a project charter activity of the project planning phase.
  B) setting a baseline project plan activity of the project planning phase.
  C) determining project standards and procedures activity of the project planning phase.
  D) describing the project scope, alternatives, and feasibility activity of the project planning phase.
  E) closing down the project activity of the project planning phase.

Question 2

Which of the following is NOT a true statement regarding project planning?
 
  A) Project planning often requires that you make numerous assumptions about resource availability and potential problems.
  B) Project planning is the second phase of the project management process.
  C) Project planning focuses on defining clear, discrete activities and the work needed to complete each activity within a single project.
  D) The repetitive nature of the project management process requires that plans be constantly monitored throughout the project and periodically updated.
  E) Monitoring project progress against the baseline project plan is the first project planning activity.


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Jmfn03

  • Sr. Member
  • ****
  • Posts: 323
Lorsum iprem. Lorsus sur ipci. Lorsem sur iprem. Lorsum sur ipdi, lorsem sur ipci. Lorsum sur iprium, valum sur ipci et, vala sur ipci. Lorsem sur ipci, lorsa sur iprem. Valus sur ipdi. Lorsus sur iprium nunc, valem sur iprium. Valem sur ipdi. Lorsa sur iprium. Lorsum sur iprium. Valem sur ipdi. Vala sur ipdi nunc, valem sur ipdi, valum sur ipdi, lorsem sur ipdi, vala sur ipdi. Valem sur iprem nunc, lorsa sur iprium. Valum sur ipdi et, lorsus sur ipci. Valem sur iprem. Valem sur ipci. Lorsa sur iprium. Lorsem sur ipci, valus sur iprem. Lorsem sur iprem nunc, valus sur iprium.
Answer Preview
Only 45% of students answer this correctly




altibaby

  • Member
  • Posts: 562
Reply 2 on: Jul 7, 2018
Thanks for the timely response, appreciate it


aliotak

  • Member
  • Posts: 326
Reply 3 on: Yesterday
Gracias!

 

Did you know?

The top five reasons that children stay home from school are as follows: colds, stomach flu (gastroenteritis), ear infection (otitis media), pink eye (conjunctivitis), and sore throat.

Did you know?

The term bacteria was devised in the 19th century by German biologist Ferdinand Cohn. He based it on the Greek word "bakterion" meaning a small rod or staff. Cohn is considered to be the father of modern bacteriology.

Did you know?

Congestive heart failure is a serious disorder that carries a reduced life expectancy. Heart failure is usually a chronic illness, and it may worsen with infection or other physical stressors.

Did you know?

Over time, chronic hepatitis B virus and hepatitis C virus infections can progress to advanced liver disease, liver failure, and hepatocellular carcinoma. Unlike other forms, more than 80% of hepatitis C infections become chronic and lead to liver disease. When combined with hepatitis B, hepatitis C now accounts for 75% percent of all cases of liver disease around the world. Liver failure caused by hepatitis C is now leading cause of liver transplants in the United States.

Did you know?

The people with the highest levels of LDL are Mexican American males and non-Hispanic black females.

For a complete list of videos, visit our video library