Author Question: Consider the following two projects: Net Cash Flow Each Period Initial Outlay 1 2 3 4 Project A ... (Read 68 times)

TVarnum

  • Hero Member
  • *****
  • Posts: 548
Consider the following two projects:
 
  Net Cash Flow Each Period
  Initial Outlay 1 2 3 4
  Project A 4,000,000 2,003,000 2,003,000 2,003,000 2,003,000
  Project B 4,000,000 0 0 0 11,000,000
  a. Calculate the net present value of each of the above projects, assuming a 14 percent discount rate.
  b. What is the internal rate of return for each of the above projects?
  c. Compare and explain the conflicting rankings of the NPVs and IRRs obtained in parts a and b above.
  d. If 14 percent is the required rate of return, and these projects are independent, what decision should be
  made?
  e. If 14 percent is the required rate of return, and the projects are mutually exclusive, what decision should be
  made?

Question 2

An ordinary annuity may be defined as:
 
  A) A series of equal payments made at regular intervals that are paid at the beginning of each period.
  B) A series of payments, which may or may not be equal in value, that are received at regular intervals at the end of each period.
  C) A series of equal payments made any time over the course of a year, extending for a period of several years.
  D) Any series of payments that occur in the future.
  E) A series of equal payments made at regular intervals that are received at the end of each period.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

flexer1n1

  • Sr. Member
  • ****
  • Posts: 373
Answer to Question 1

a. NPV of A = 1,836,166 NPV of B = 2,512,883
b. IRR of A = 35.0 IRR of B = 28.78
c. B has more distant cash flows, thus its IRR is less while its NPV is greater. This time disparity is one of IRR's
ranking problems.
d. If these projects are independent, we would accept them both because they each have a positive NPV.
e. If these projects are mutually exclusive, we would select B because it has the highest positive NPV.

Answer to Question 2

E




TVarnum

  • Member
  • Posts: 548
Reply 2 on: Jul 10, 2018
Thanks for the timely response, appreciate it


abro1885

  • Member
  • Posts: 337
Reply 3 on: Yesterday
Great answer, keep it coming :)

 

Did you know?

Multiple experimental evidences have confirmed that at the molecular level, cancer is caused by lesions in cellular DNA.

Did you know?

To maintain good kidney function, you should drink at least 3 quarts of water daily. Water dilutes urine and helps prevent concentrations of salts and minerals that can lead to kidney stone formation. Chronic dehydration is a major contributor to the development of kidney stones.

Did you know?

Critical care patients are twice as likely to receive the wrong medication. Of these errors, 20% are life-threatening, and 42% require additional life-sustaining treatments.

Did you know?

In the United States, congenital cytomegalovirus causes one child to become disabled almost every hour. CMV is the leading preventable viral cause of development disability in newborns. These disabilities include hearing or vision loss, and cerebral palsy.

Did you know?

Warfarin was developed as a consequence of the study of a strange bleeding disorder that suddenly occurred in cattle on the northern prairies of the United States in the early 1900s.

For a complete list of videos, visit our video library