Author Question: Based on historical weather data, a particular project is expected to be impacted by 6 adverse ... (Read 66 times)

cagreen833

  • Hero Member
  • *****
  • Posts: 544
Based on historical weather data, a particular project is expected to be impacted by 6 adverse weather days. Using one of the procedures described in this chapter, make the appropriate allowance for adverse weather and solve the network for the basic scheduling information. For each activity, .show the computed value of early start, early finish, late start, late finish, total float, and free float.
 
  What will be an ideal response?

Question 2

Describe factors that might impact the level of detail used in a schedule.
 
  What will be an ideal response?



Ahnyah

  • Sr. Member
  • ****
  • Posts: 336
Answer to Question 1

There are a variety of answers that might be given for this problem. One
suggestion in the text was to include a weather delay activity late in the network. This has
been done below by the addition of activity W. Adjustments could also be made to the
individual activity durations. This would result in fractions of days unless some type of
rounding was employed. Regardless of the approach, the six days of weather delays must
be incorporated such that the duration is extended by six days.

Answer to Question 2

Perhaps the primary factor is the end user of the schedule. If the user of the
schedule will use the schedule to monitor performance, less detail will be required
than when the schedule is used to plan work activities. Where there are many users, it
is a function of the maximum amount of detail that will be required or expected by
one of the users. In some instances, the contract will dictate the level of detail that is
to be used. Other factors that might impact the schedule detail include project complexity,
number of subcontractors, and how much the schedule will be used to plan the work.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The human body's pharmacokinetics are quite varied. Our hair holds onto drugs longer than our urine, blood, or saliva. For example, alcohol can be detected in the hair for up to 90 days after it was consumed. The same is true for marijuana, cocaine, ecstasy, heroin, methamphetamine, and nicotine.

Did you know?

Bisphosphonates were first developed in the nineteenth century. They were first investigated for use in disorders of bone metabolism in the 1960s. They are now used clinically for the treatment of osteoporosis, Paget's disease, bone metastasis, multiple myeloma, and other conditions that feature bone fragility.

Did you know?

The U.S. Pharmacopeia Medication Errors Reporting Program states that approximately 50% of all medication errors involve insulin.

Did you know?

ACTH levels are normally highest in the early morning (between 6 and 8 A.M.) and lowest in the evening (between 6 and 11 P.M.). Therefore, a doctor who suspects abnormal levels looks for low ACTH in the morning and high ACTH in the evening.

Did you know?

Long-term mental and physical effects from substance abuse include: paranoia, psychosis, immune deficiencies, and organ damage.

For a complete list of videos, visit our video library