What types of claims could arise related to the use of Building Information Modeling software on construction projects?
 
  What will be an ideal response?

Question 2

Pretreatment of boiler feedwater __________________.
 
  A. consists of heating, softening and reverse osmosis treatment, and is done to limit the amount of chemicals necessary
  B. consists of chemical treatment and is used to raise the Ph of the feedwater
  C. consists of chemical treatment and is used to lower the Ph of the feedwater
  D. is only used on large boilers operating for a power utility



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

mistyjohnson

  • Sr. Member
  • ****
  • Posts: 331
Answer to Question 1

The potential types of claims that could arise related to the use of Building Information Modeling are the following:

a) Liability issues related to generating three dimensional models using drawings
from several different firms and who would be responsible for errors.
b) Disputes arising from software incompatibility and inaccurate data being
uploaded into the BIM software, as a result of incompatibility.
c) Disputes arising from changes being made after drawings are uploaded into the
three dimensional models on the two dimensional drawings.
d) Disputes from changes resulting from clashes between construction elements
designed by members of different firms.
e) Disputes resulting from how construction elements are displayed in a three
dimensional model versus how they are shown on individual engineering or shop
drawings.
f) Disputes prompted by the engineering drawings not containing all of the changes
that were made on the three dimensional model, although the three dimensional
modeling software is suppose to transpose the three dimensional model back
into accurate two dimensional drawings.

Answer to Question 2

A




burchfield96

  • Member
  • Posts: 610
Reply 2 on: Jul 26, 2018
Great answer, keep it coming :)


matt95

  • Member
  • Posts: 317
Reply 3 on: Yesterday
Thanks for the timely response, appreciate it

 

Did you know?

It is believed that humans initially contracted crabs from gorillas about 3 million years ago from either sleeping in gorilla nests or eating the apes.

Did you know?

Aspirin may benefit 11 different cancers, including those of the colon, pancreas, lungs, prostate, breasts, and leukemia.

Did you know?

The first oncogene was discovered in 1970 and was termed SRC (pronounced "SARK").

Did you know?

Elderly adults are living longer, and causes of death are shifting. At the same time, autopsy rates are at or near their lowest in history.

Did you know?

HIV testing reach is still limited. An estimated 40% of people with HIV (more than 14 million) remain undiagnosed and do not know their infection status.

For a complete list of videos, visit our video library