Author Question: Project management set up to complete a project in consecutive phases is called a. agile. b. ... (Read 238 times)

tnt_battle

  • Hero Member
  • *****
  • Posts: 556
Project management set up to complete a project in consecutive phases is called
 a. agile.
  b. Gantt.
  c. traditional.
  d. waterfall.

Question 2

Choose the correct word or words in parentheses. A car in the parking lot has (its, it's) lights on.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

jennafosdick

  • Sr. Member
  • ****
  • Posts: 345
Answer to Question 1

d

Answer to Question 2

its




tnt_battle

  • Member
  • Posts: 556
Reply 2 on: Jun 23, 2018
Excellent


amynguyen1221

  • Member
  • Posts: 355
Reply 3 on: Yesterday
YES! Correct, THANKS for helping me on my review

 

Did you know?

Interferon was scarce and expensive until 1980, when the interferon gene was inserted into bacteria using recombinant DNA technology, allowing for mass cultivation and purification from bacterial cultures.

Did you know?

A seasonal flu vaccine is the best way to reduce the chances you will get seasonal influenza and spread it to others.

Did you know?

All patients with hyperparathyroidism will develop osteoporosis. The parathyroid glands maintain blood calcium within the normal range. All patients with this disease will continue to lose calcium from their bones every day, and there is no way to prevent the development of osteoporosis as a result.

Did you know?

Individuals are never “cured” of addictions. Instead, they learn how to manage their disease to lead healthy, balanced lives.

Did you know?

Children of people with alcoholism are more inclined to drink alcohol or use hard drugs. In fact, they are 400 times more likely to use hard drugs than those who do not have a family history of alcohol addiction.

For a complete list of videos, visit our video library