This topic contains a solution. Click here to go to the answer

Author Question: To determine how to crash activity times a. normal activity costs and costs under maximum crashing ... (Read 93 times)

fasfsadfdsfa

  • Hero Member
  • *****
  • Posts: 554
To determine how to crash activity times
 a. normal activity costs and costs under maximum crashing must be known.
  b. shortest times with crashing must be known.
  c. realize that new paths may become critical.
  d. All of the alternatives are true.

Question 2

The difference between the observed value of the dependent variable and the value predicted by using the estimated regression equation is called _____.
 a. the standard error
  b. a residual
  c. a prediction interval
  d. the variance



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Chocorrol77

  • Sr. Member
  • ****
  • Posts: 313
Answer to Question 1

D

Answer to Question 2

b




fasfsadfdsfa

  • Member
  • Posts: 554
Reply 2 on: Jun 24, 2018
YES! Correct, THANKS for helping me on my review


patma1981

  • Member
  • Posts: 292
Reply 3 on: Yesterday
Great answer, keep it coming :)

 

Did you know?

The term pharmacology is derived from the Greek words pharmakon("claim, medicine, poison, or remedy") and logos ("study").

Did you know?

Malaria was not eliminated in the United States until 1951. The term eliminated means that no new cases arise in a country for 3 years.

Did you know?

Street names for barbiturates include reds, red devils, yellow jackets, blue heavens, Christmas trees, and rainbows. They are commonly referred to as downers.

Did you know?

There are more bacteria in your mouth than there are people in the world.

Did you know?

After 5 years of being diagnosed with rheumatoid arthritis, one every three patients will no longer be able to work.

For a complete list of videos, visit our video library