Author Question: A manufacturer makes two products, doors and windows. Each must be processed through two work areas. ... (Read 83 times)

michelleunicorn

  • Hero Member
  • *****
  • Posts: 565
A manufacturer makes two products, doors and windows. Each must be processed through two work areas. Work area 1 has 60 hours of available production time per week. Work area 2 has 48 hours of available production time per week. Manufacturing of a door requires 4 hours in work area 1 and 2 hours in work area 2 . Manufacturing of a window requires 2 hours in work area 1 and 4 hours in work area 2 . Profit is 8 per door and 6 per window.
 a. Define decision variables that will tell how many units to build (doors and windows) per week.
  b. Develop an objective function that will maximize total profit per week.
  c. Develop production constraints for work area 1 and 2.

Question 2

The degrees of freedom for a contingency table with 6 rows and 3 columns is
 a. 18
  b. 15
  c. 6
  d. 10



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

paavo

  • Sr. Member
  • ****
  • Posts: 301
Answer to Question 1

a. Let D = the number of doors to build per week
Let N = the number of windows to build per week
b. Weekly Profit = 8D + 6W
c. 4D + 2W  60
2D + 4W  48

Answer to Question 2

D




michelleunicorn

  • Member
  • Posts: 565
Reply 2 on: Jun 24, 2018
Gracias!


kswal303

  • Member
  • Posts: 316
Reply 3 on: Yesterday
Excellent

 

Did you know?

Many of the drugs used by neuroscientists are derived from toxic plants and venomous animals (such as snakes, spiders, snails, and puffer fish).

Did you know?

Every 10 seconds, a person in the United States goes to the emergency room complaining of head pain. About 1.2 million visits are for acute migraine attacks.

Did you know?

There are over 65,000 known species of protozoa. About 10,000 species are parasitic.

Did you know?

There can actually be a 25-hour time difference between certain locations in the world. The International Date Line passes between the islands of Samoa and American Samoa. It is not a straight line, but "zig-zags" around various island chains. Therefore, Samoa and nearby islands have one date, while American Samoa and nearby islands are one day behind. Daylight saving time is used in some islands, but not in others—further shifting the hours out of sync with natural time.

Did you know?

The most destructive flu epidemic of all times in recorded history occurred in 1918, with approximately 20 million deaths worldwide.

For a complete list of videos, visit our video library