Author Question: Set up a construction project flow system so that all parties are assured of payment and adequate ... (Read 70 times)

lidoalex

  • Hero Member
  • *****
  • Posts: 538
Set up a construction project flow system so that all parties are assured of payment and adequate performance.

Question 2

A lease of premises that violate the city fire code is:
 A) Void.
 B) Valid as long as the premises are habitable.
 C) Valid as long as the tenant is warned.
 D) Valid until the tenant is aware of the code problems.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

IRincones

  • Sr. Member
  • ****
  • Posts: 321
Answer to Question 1

Students should use third party/architect's certificate system; retainage should be used; flowdown clause for general; payment and performance bonds.

Answer to Question 2

A





 

Did you know?

Multiple sclerosis is a condition wherein the body's nervous system is weakened by an autoimmune reaction that attacks the myelin sheaths of neurons.

Did you know?

Chronic marijuana use can damage the white blood cells and reduce the immune system's ability to respond to disease by as much as 40%. Without a strong immune system, the body is vulnerable to all kinds of degenerative and infectious diseases.

Did you know?

Recent studies have shown that the number of medication errors increases in relation to the number of orders that are verified per pharmacist, per work shift.

Did you know?

Thyroid conditions may make getting pregnant impossible.

Did you know?

Symptoms of kidney problems include a loss of appetite, back pain (which may be sudden and intense), chills, abdominal pain, fluid retention, nausea, the urge to urinate, vomiting, and fever.

For a complete list of videos, visit our video library