Author Question: A bridge construction project, accounted for in a Capital Projects Fund, is in Year 2 of an ... (Read 66 times)

gbarreiro

  • Hero Member
  • *****
  • Posts: 566
A bridge construction project, accounted for in a Capital Projects Fund, is in Year 2 of an anticipated three year construction period. In Year 1, costs of 300,000 were incurred. In Year 2, 1,530,000 of costs were incurred.
 
  What entry would be necessary in the General Capital Assets accounts for Year 2?
 
   Debit Credit
  A. Capital Outlay
   Cash 1,530,000
  1,530,000
  B. Construction in progress
   Cash 1,530,000
  1,530,000
  C. Construction in progress
   Net investment in capital assets 1,530,000
  1,530,000
  D. Construction in progress
   Net investment in capital assets 1,830,000
  1,830,000

Question 2

It is critical for accountants to understand enterprise resource planning (ERP) systems.
  Indicate whether the statement is true or false



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

pami445

  • Sr. Member
  • ****
  • Posts: 303
Answer to Question 1

C

Answer to Question 2

T




gbarreiro

  • Member
  • Posts: 566
Reply 2 on: Jul 5, 2018
Wow, this really help


Mochi

  • Member
  • Posts: 300
Reply 3 on: Yesterday
YES! Correct, THANKS for helping me on my review

 

Did you know?

When taking monoamine oxidase inhibitors, people should avoid a variety of foods, which include alcoholic beverages, bean curd, broad (fava) bean pods, cheese, fish, ginseng, protein extracts, meat, sauerkraut, shrimp paste, soups, and yeast.

Did you know?

Most childhood vaccines are 90–99% effective in preventing disease. Side effects are rarely serious.

Did you know?

Children with strabismus (crossed eyes) can be treated. They are not able to outgrow this condition on their own, but with help, it can be more easily corrected at a younger age. It is important for infants to have eye examinations as early as possible in their development and then another at age 2 years.

Did you know?

The immune system needs 9.5 hours of sleep in total darkness to recharge completely.

Did you know?

Aspirin is the most widely used drug in the world. It has even been recognized as such by the Guinness Book of World Records.

For a complete list of videos, visit our video library