Author Question: Direct manufacturing labor and direct materials variances, missing data. (CMA, heavily adapted) ... (Read 120 times)

go.lag

  • Hero Member
  • *****
  • Posts: 667
Direct manufacturing labor and direct materials variances, missing data.
 
  (CMA, heavily adapted) Young Bay Surfboards manufactures fiberglass surfboards. The standard cost of direct materials and direct manufacturing labor is 223 per board. This includes 40 pounds of direct materials, at the budgeted price of 2 per pound, and 10 hours of direct manufacturing labor, at the budgeted rate of 14.30 per hour. Following are additional data for the month of July:
 
  There were no beginning inventories.
 
  Required:
  1. Compute direct manufacturing labor variances for July.
  2. Compute the actual pounds of direct materials used in production in July.
  3. Calculate the actual price per pound of direct materials purchased.
  4. Calculate the direct materials price variance.

Question 2

Failure to record the adjusting entry for depreciation will overstate assets on the balance sheet.
  Indicate whether the statement is true or false



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Athena23

  • Sr. Member
  • ****
  • Posts: 305
Answer to Question 1

1.
Flexible Budget
(Budgeted Input
Actual Costs Qty. Allowed for
Incurred (Actual Actual Input Qty. Actual Output
Input Qty. Actual Price)  Budgeted Price  Budgeted Price)
Direct mfg. labor 594,500a 586,300b 786,500c

8,200 U 200,200 F
Price variance Efficiency variance

192,000 F
Flexible-budget variance

a Given (or 41,000 hours  14.50/hour)
b 41,000 hours  14.30/hour = 735,000
c 5,500 units  10 hours/unit  14.30/hour = 786,500

2. The favorable direct materials efficiency variance of 1,700 indicates that fewer pounds of direct materials were actually used than the budgeted quantity allowed for actual output.

=

= 850 pounds

Budgeted pounds allowed for the output achieved = 5,500  40 = 220,000 pounds

Actual pounds of direct materials used = 220,000  850 = 219,150 pounds

3. Actual price paid per pound = 432,000/160,000
= 2.70 per pound

4. Actual Costs Incurred Actual Input
(Actual Input  Actual Price) Budgeted Price
432,000a 320,000b

112,000 U
Price variance

a Given
b 160,000 pounds  2/pound = 320,000

Answer to Question 2

T




go.lag

  • Member
  • Posts: 667
Reply 2 on: Jul 6, 2018
Thanks for the timely response, appreciate it


flexer1n1

  • Member
  • Posts: 373
Reply 3 on: Yesterday
Excellent

 

Did you know?

Between 1999 and 2012, American adults with high total cholesterol decreased from 18.3% to 12.9%

Did you know?

Illness; diuretics; laxative abuse; hot weather; exercise; sweating; caffeine; alcoholic beverages; starvation diets; inadequate carbohydrate consumption; and diets high in protein, salt, or fiber can cause people to become dehydrated.

Did you know?

Coca-Cola originally used coca leaves and caffeine from the African kola nut. It was advertised as a therapeutic agent and "pickerupper." Eventually, its formulation was changed, and the coca leaves were removed because of the effects of regulation on cocaine-related products.

Did you know?

Pregnant women usually experience a heightened sense of smell beginning late in the first trimester. Some experts call this the body's way of protecting a pregnant woman from foods that are unsafe for the fetus.

Did you know?

Human neurons are so small that they require a microscope in order to be seen. However, some neurons can be up to 3 feet long, such as those that extend from the spinal cord to the toes.

For a complete list of videos, visit our video library