Author Question: In the context of a systems development project, which of the following statements is true ofthe ... (Read 37 times)

Alainaaa8

  • Hero Member
  • *****
  • Posts: 576
In the context of a systems development project, which of the following statements is true ofthe relationships between requirements, cost, and time?
 
  A) Increasing the time for the completion of a project always increases the cost of the project.
  B) Increasing the cost of a project will always reduce the time required to finish the project.
  C) Reducing the requirements in a project rarely affects the time required to finish the project.
  D) Reducing the number of requirements in a project reduces the overall cost of the project.

Question 2

To create a query in Microsoft Access, one must drag columns out of the required tables intothe grid in the lower part of the query definition form.
 
  Indicate whether the statement is true or false



hugthug12

  • Sr. Member
  • ****
  • Posts: 329
Answer to Question 1

D

Answer to Question 2

TRUE



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The use of salicylates dates back 2,500 years to Hippocrates's recommendation of willow bark (from which a salicylate is derived) as an aid to the pains of childbirth. However, overdosage of salicylates can harm body fluids, electrolytes, the CNS, the GI tract, the ears, the lungs, the blood, the liver, and the kidneys and cause coma or death.

Did you know?

All adverse reactions are commonly charted in red ink in the patient's record and usually are noted on the front of the chart. Failure to follow correct documentation procedures may result in malpractice lawsuits.

Did you know?

The first successful kidney transplant was performed in 1954 and occurred in Boston. A kidney from an identical twin was transplanted into his dying brother's body and was not rejected because it did not appear foreign to his body.

Did you know?

There used to be a metric calendar, as well as metric clocks. The metric calendar, or "French Republican Calendar" divided the year into 12 months, but each month was divided into three 10-day weeks. Each day had 10 decimal hours. Each hour had 100 decimal minutes. Due to lack of popularity, the metric clocks and calendars were ended in 1795, three years after they had been first marketed.

Did you know?

Serum cholesterol testing in adults is recommended every 1 to 5 years. People with diabetes and a family history of high cholesterol should be tested even more frequently.

For a complete list of videos, visit our video library