Author Question: Explain the four phases of project management. What will be an ideal ... (Read 78 times)

dbose

  • Hero Member
  • *****
  • Posts: 597
Explain the four phases of project management.
 
  What will be an ideal response?

Question 2

Databases that carry their data in the form of tables and represent relationships using foreignkeys are called ________ databases.
 
  A) hierarchical
  B) network
  C) relational
  D) object



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

cegalasso

  • Sr. Member
  • ****
  • Posts: 295
Answer to Question 1

The four phases of project management are:
1. Starting phase: The fundamental purpose of the starting phase is to set the ground rules for the
project and the team. Other tasks during the starting phase are to set the scope of the project and
to establish an initial budget.
2. Planning phase: The purpose of the planning phase is to determine who will do what and by
when. Work activities are defined, and resources such as personnel, budget, and equipment are
assigned to them. Tasks often depend on one other. The project budget is usually revised during
the planning phase as well.
3. Doing phase: Project tasks are accomplished during the doing phase. The key management
challenge here is to ensure that tasks are accomplished on time, and, if not, to identify schedule
problems as early as possible. As work progresses, it is often necessary to add or delete tasks,
change task assignments, add or remove task labor or other resources, and so forth. Another
important task is to document and report project progress.
4. Finalizing phase: In this phase, the team needs to document its results, document information
for future teams, close down the project, and disband the team.

Answer to Question 2

C



dbose

  • Hero Member
  • *****
  • Posts: 597

cegalasso

  • Sr. Member
  • ****
  • Posts: 295

 

Did you know?

The top five reasons that children stay home from school are as follows: colds, stomach flu (gastroenteritis), ear infection (otitis media), pink eye (conjunctivitis), and sore throat.

Did you know?

Certain chemicals, after ingestion, can be converted by the body into cyanide. Most of these chemicals have been removed from the market, but some old nail polish remover, solvents, and plastics manufacturing solutions can contain these substances.

Did you know?

Many supplement containers do not even contain what their labels say. There are many documented reports of products containing much less, or more, that what is listed on their labels. They may also contain undisclosed prescription drugs and even contaminants.

Did you know?

Drug abusers experience the following scenario: The pleasure given by their drug (or drugs) of choice is so strong that it is difficult to eradicate even after years of staying away from the substances involved. Certain triggers may cause a drug abuser to relapse. Research shows that long-term drug abuse results in significant changes in brain function that persist long after an individual stops using drugs. It is most important to realize that the same is true of not just illegal substances but alcohol and tobacco as well.

Did you know?

During the twentieth century, a variant of the metric system was used in Russia and France in which the base unit of mass was the tonne. Instead of kilograms, this system used millitonnes (mt).

For a complete list of videos, visit our video library