If a project is selected, what is the most likely next step?
 
  A) The project will begin.
  B) The project will be funded.
  C) The project has to be signed off by management.
  D) The project is no longer considered.

Question 2

________ is a process of considering short- and long- term projects.
 
  A) Project selection
  B) Project identification
  C) Project determination
  D) Project analysis



carojassy25

  • Sr. Member
  • ****
  • Posts: 299
Answer to Question 1

B

Answer to Question 2

A



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Today, nearly 8 out of 10 pregnant women living with HIV (about 1.1 million), receive antiretrovirals.

Did you know?

Sildenafil (Viagra®) has two actions that may be of consequence in patients with heart disease. It can lower the blood pressure, and it can interact with nitrates. It should never be used in patients who are taking nitrates.

Did you know?

Elderly adults are at greatest risk of stroke and myocardial infarction and have the most to gain from prophylaxis. Patients ages 60 to 80 years with blood pressures above 160/90 mm Hg should benefit from antihypertensive treatment.

Did you know?

Adult head lice are gray, about ? inch long, and often have a tiny dot on their backs. A female can lay between 50 and 150 eggs within the several weeks that she is alive. They feed on human blood.

Did you know?

Many medications that are used to treat infertility are injected subcutaneously. This is easy to do using the anterior abdomen as the site of injection but avoiding the area directly around the belly button.

For a complete list of videos, visit our video library