Author Question: Which of the following project management activities is associated with project initiation? A) ... (Read 64 times)

debasdf

  • Hero Member
  • *****
  • Posts: 570
Which of the following project management activities is associated with project initiation?
 
  A) Estimating resources and creating a detailed resource plan
  B) Describing project scope, alternatives, and feasibility
  C) Establishing a relationship with the customer
  D) Identifying and assessing risks
  E) Closing down the project

Question 2

In which phase will the systems analyst convert the description of the recommended alternative solution into logical and then physical system specifications?
 
  A) Systems planning and selection
  B) Systems conversion
  C) Systems analysis
  D) Systems design
  E) Systems implementation and operation



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Juro

  • Sr. Member
  • ****
  • Posts: 337
Answer to Question 1

C
Explanation: C) A strong relationship with the customer does establish trust.

Answer to Question 2

D
Explanation: D) During the design phase, all specifications are written.




debasdf

  • Member
  • Posts: 570
Reply 2 on: Jul 7, 2018
:D TYSM


smrtceo

  • Member
  • Posts: 344
Reply 3 on: Yesterday
Thanks for the timely response, appreciate it

 

Did you know?

Though the United States has largely rejected the metric system, it is used for currency, as in 100 pennies = 1 dollar. Previously, the British currency system was used, with measurements such as 12 pence to the shilling, and 20 shillings to the pound.

Did you know?

A headache when you wake up in the morning is indicative of sinusitis. Other symptoms of sinusitis can include fever, weakness, tiredness, a cough that may be more severe at night, and a runny nose or nasal congestion.

Did you know?

Most women experience menopause in their 50s. However, in 1994, an Italian woman gave birth to a baby boy when she was 61 years old.

Did you know?

The ratio of hydrogen atoms to oxygen in water (H2O) is 2:1.

Did you know?

The first oncogene was discovered in 1970 and was termed SRC (pronounced "SARK").

For a complete list of videos, visit our video library