Author Question: A superintendent plans to build a 3,000 ft.2 tee. He wants to place a 12-inch layer of loamy sand ... (Read 58 times)

vicotolentino

  • Hero Member
  • *****
  • Posts: 552
A superintendent plans to build a 3,000 ft.2 tee. He wants to place a 12-inch layer of loamy sand over the existing soil. One cubic yard of the loamy sand equals 1.2 tons. How many tons are needed?
 
  What will be an ideal response?

Question 2

A sports field is to be topdressed with 0.25 inch of soil. How many cubic yards of soil are needed?
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

ju

  • Sr. Member
  • ****
  • Posts: 325
Answer to Question 1

133.33 tons

Answer to Question 2

46.3 cubic yards




vicotolentino

  • Member
  • Posts: 552
Reply 2 on: Jul 21, 2018
Thanks for the timely response, appreciate it


irishcancer18

  • Member
  • Posts: 310
Reply 3 on: Yesterday
Gracias!

 

Did you know?

The ratio of hydrogen atoms to oxygen in water (H2O) is 2:1.

Did you know?

Although not all of the following muscle groups are commonly used, intramuscular injections may be given into the abdominals, biceps, calves, deltoids, gluteals, laterals, pectorals, quadriceps, trapezoids, and triceps.

Did you know?

Critical care patients are twice as likely to receive the wrong medication. Of these errors, 20% are life-threatening, and 42% require additional life-sustaining treatments.

Did you know?

More than 34,000 trademarked medication names and more than 10,000 generic medication names are in use in the United States.

Did you know?

Symptoms of kidney problems include a loss of appetite, back pain (which may be sudden and intense), chills, abdominal pain, fluid retention, nausea, the urge to urinate, vomiting, and fever.

For a complete list of videos, visit our video library