This topic contains a solution. Click here to go to the answer

Author Question: In a firm, fixed price contract, the contractor's profit is _____. a. tied to project schedule ... (Read 59 times)

savannahhooper

  • Hero Member
  • *****
  • Posts: 576
In a firm, fixed price contract, the contractor's profit is _____.
 
  a. tied to project schedule performance
  b. subject to penalties and incentives
  c. negotiated separately from labor and material costs
  d. incorporated into the bid

Question 2

When a person is promoted to crew leader, the amount of time they spend on craft work _____.
 
  a. stays the same
  b. doubles
  c. decreases
  d. increases



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

angrybirds13579

  • Sr. Member
  • ****
  • Posts: 344
Answer to Question 1

d

Answer to Question 2

c




savannahhooper

  • Member
  • Posts: 576
Reply 2 on: Jul 24, 2018
Great answer, keep it coming :)


jackie

  • Member
  • Posts: 324
Reply 3 on: Yesterday
Thanks for the timely response, appreciate it

 

Did you know?

Your chance of developing a kidney stone is 1 in 10. In recent years, approximately 3.7 million people in the United States were diagnosed with a kidney disease.

Did you know?

Pregnant women usually experience a heightened sense of smell beginning late in the first trimester. Some experts call this the body's way of protecting a pregnant woman from foods that are unsafe for the fetus.

Did you know?

The average adult has about 21 square feet of skin.

Did you know?

Less than one of every three adults with high LDL cholesterol has the condition under control. Only 48.1% with the condition are being treated for it.

Did you know?

The heart is located in the center of the chest, with part of it tipped slightly so that it taps against the left side of the chest.

For a complete list of videos, visit our video library