Author Question: When the owner/engineer's inspector or the resident project representative or the contractor's ... (Read 73 times)

krzymel

  • Hero Member
  • *****
  • Posts: 548
When the owner/engineer's inspector or the resident project representative or the contractor's superintendent leaves the project site for a while, it is permissible to do which of the following:
 
  A. Leave the site without notifying anyone.
   B. Leave word that you will be out for a while, but it is not necessary to say where or leave a number.
   C. Close the job for the day.
   D. Notify your office of your absence and leave a number where you can be reached.

Question 2

What are the responsibilities of owners during construction projects?
 
  What will be an ideal response?



ms_sulzle

  • Sr. Member
  • ****
  • Posts: 320
Answer to Question 1

D

Answer to Question 2

Owners are responsible for financing projects, the initial planning of projects, providing information to designers on project requirements, and the operating and maintenance requirement of facilities.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The use of salicylates dates back 2,500 years to Hippocrates's recommendation of willow bark (from which a salicylate is derived) as an aid to the pains of childbirth. However, overdosage of salicylates can harm body fluids, electrolytes, the CNS, the GI tract, the ears, the lungs, the blood, the liver, and the kidneys and cause coma or death.

Did you know?

Cancer has been around as long as humankind, but only in the second half of the twentieth century did the number of cancer cases explode.

Did you know?

The National Institutes of Health have supported research into acupuncture. This has shown that acupuncture significantly reduced pain associated with osteoarthritis of the knee, when used as a complement to conventional therapies.

Did you know?

Malaria mortality rates are falling. Increased malaria prevention and control measures have greatly improved these rates. Since 2000, malaria mortality rates have fallen globally by 60% among all age groups, and by 65% among children under age 5.

Did you know?

There used to be a metric calendar, as well as metric clocks. The metric calendar, or "French Republican Calendar" divided the year into 12 months, but each month was divided into three 10-day weeks. Each day had 10 decimal hours. Each hour had 100 decimal minutes. Due to lack of popularity, the metric clocks and calendars were ended in 1795, three years after they had been first marketed.

For a complete list of videos, visit our video library