Question 1
The MPS calls for 50 units of Product A and 60 of B. There are currently 25 of Product B on hand. Each A requires 2 of Part C; each B requires 5 of C. There are 160 units of C available. The net requirements for C are
◦ 690.
◦ 700.
◦ 240.
◦ 115.
◦ 175.
Question 2
The MPS calls for 110 units of Product A. There are currently 60 of Product A on hand. Each A requires 4 of Part B. There are 20 units of B available. The net requirements for B are
◦ 440.
◦ 120.
◦ 180.
◦ 240.
◦ 20.