Maintenance costs at Red Dot Manufacturing over the past six months are listed in the following table.

MonthMaintenance costMachine hours
January$9,50015,800
February$9,86017,300
March$8,60014,500
April$8,84016,100
May$8,60017,100
June$8,10015,500


Using the high low method, what is the variable maintenance cost per machine hour at Red Dot Manufacturing?
◦ $2.22
◦ $0.57
◦ $0.59
◦ $0.45


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by Sufayan.ah on Jan 5, 2020

cclemon1

  • Sr. Member
  • ****
  • Posts: 312
Lorsum iprem. Lorsus sur ipci. Lorsem sur iprem. Lorsum sur ipdi, lorsem sur ipci. Lorsum sur iprium, valum sur ipci et, vala sur ipci. Lorsem sur ipci, lorsa sur iprem. Valus sur ipdi. Lorsus sur iprium nunc, valem sur iprium. Valem sur ipdi. Lorsa sur iprium. Lorsum sur iprium. Valem sur ipdi. Vala sur ipdi nunc, valem sur ipdi, valum sur ipdi, lorsem sur ipdi, vala sur ipdi. Valem sur iprem nunc, lorsa sur iprium. Valum sur ipdi et, lorsus sur ipci. Valem sur iprem. Valem sur ipci. Lorsa sur iprium. Lorsem sur ipci, valus sur iprem. Lorsem sur iprem nunc, valus sur iprium.
Answer Preview
Only 64% of students answer this correctly



Brittanyd9008

  • Hero Member
  • *****
  • Posts: 500
Maintenance costs at Red Dot Manufacturing over the past six months are listed in the following table.

MonthMaintenance costMachine hours
January$9,50015,800
February$9,86017,300
March$8,60014,500
April$8,84016,100
May$8,60017,100
June$8,10015,500


Using the high low method, what is the monthly fixed maintenance cost at Red Dot Manufacturing?
◦ $2,075
◦ $18,460
◦ $1,260
◦ $7,785




scienceeasy

  • Hero Member
  • *****
  • Posts: 565
Maintenance costs at Red Dot Manufacturing over the past six months are listed in the following table.

MonthMaintenance costMachine hours
January$9,50015,800
February$9,86017,300
March$8,60014,500
April$8,84016,100
May$8,60017,100
June$8,10015,500


Using the high low method, what is the total maintenance costs at Red Dot Manufacturing if 18,000 machine hours were used?
◦ $15,660
◦ $7,875
◦ $10,175
◦ $9,950




 

Did you know?

During the twentieth century, a variant of the metric system was used in Russia and France in which the base unit of mass was the tonne. Instead of kilograms, this system used millitonnes (mt).

Did you know?

The average adult has about 21 square feet of skin.

Did you know?

In ancient Rome, many of the richer people in the population had lead-induced gout. The reason for this is unclear. Lead poisoning has also been linked to madness.

Did you know?

The Babylonians wrote numbers in a system that used 60 as the base value rather than the number 10. They did not have a symbol for "zero."

Did you know?

About 3.2 billion people, nearly half the world population, are at risk for malaria. In 2015, there are about 214 million malaria cases and an estimated 438,000 malaria deaths.

For a complete list of videos, visit our video library