In a network diagram, an activity:
◦ must always have a single, precise estimate for the time duration.
◦ should always be something the company has had experience with.
◦ is the largest unit of work effort consuming both time and resources that a project manager can schedule and control.
◦ is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control.