Author Question: Activities following a node a. can begin as soon as any activity preceding the node has been ... (Read 88 times)

formula1

  • Hero Member
  • *****
  • Posts: 666
Activities following a node
 a. can begin as soon as any activity preceding the node has been completed.
  b. have an earliest start time equal to the largest of the earliest finish times for all activities entering the node.
  c. have a latest start time equal to the largest of the earliest finish times for all activities entering the node.
  d. None of the alternatives is correct.

Question 2

In testing for the equality of k population means, the number of treatments is _____.
 a. k
  b. k-1
  c. nT
  d. nT - k



jaymee143

  • Sr. Member
  • ****
  • Posts: 341
Answer to Question 1

B

Answer to Question 2

d



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

It is believed that the Incas used anesthesia. Evidence supports the theory that shamans chewed cocoa leaves and drilled holes into the heads of patients (letting evil spirits escape), spitting into the wounds they made. The mixture of cocaine, saliva, and resin numbed the site enough to allow hours of drilling.

Did you know?

Never take aspirin without food because it is likely to irritate your stomach. Never give aspirin to children under age 12. Overdoses of aspirin have the potential to cause deafness.

Did you know?

Increased intake of vitamin D has been shown to reduce fractures up to 25% in older people.

Did you know?

There are more bacteria in your mouth than there are people in the world.

Did you know?

It is important to read food labels and choose foods with low cholesterol and saturated trans fat. You should limit saturated fat to no higher than 6% of daily calories.

For a complete list of videos, visit our video library