Author Question: Activities following a node a. can begin as soon as any activity preceding the node has been ... (Read 114 times)

formula1

  • Hero Member
  • *****
  • Posts: 666
Activities following a node
 a. can begin as soon as any activity preceding the node has been completed.
  b. have an earliest start time equal to the largest of the earliest finish times for all activities entering the node.
  c. have a latest start time equal to the largest of the earliest finish times for all activities entering the node.
  d. None of the alternatives is correct.

Question 2

In testing for the equality of k population means, the number of treatments is _____.
 a. k
  b. k-1
  c. nT
  d. nT - k



jaymee143

  • Sr. Member
  • ****
  • Posts: 341
Answer to Question 1

B

Answer to Question 2

d



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Every 10 seconds, a person in the United States goes to the emergency room complaining of head pain. About 1.2 million visits are for acute migraine attacks.

Did you know?

Nitroglycerin is used to alleviate various heart-related conditions, and it is also the chief component of dynamite (but mixed in a solid clay base to stabilize it).

Did you know?

During pregnancy, a woman is more likely to experience bleeding gums and nosebleeds caused by hormonal changes that increase blood flow to the mouth and nose.

Did you know?

Historic treatments for rheumatoid arthritis have included gold salts, acupuncture, a diet consisting of apples or rhubarb, nutmeg, nettles, bee venom, bracelets made of copper, prayer, rest, tooth extractions, fasting, honey, vitamins, insulin, snow collected on Christmas, magnets, and electric convulsion therapy.

Did you know?

During the twentieth century, a variant of the metric system was used in Russia and France in which the base unit of mass was the tonne. Instead of kilograms, this system used millitonnes (mt).

For a complete list of videos, visit our video library