Author Question: Activities following a node a. can begin as soon as any activity preceding the node has been ... (Read 112 times)

formula1

  • Hero Member
  • *****
  • Posts: 666
Activities following a node
 a. can begin as soon as any activity preceding the node has been completed.
  b. have an earliest start time equal to the largest of the earliest finish times for all activities entering the node.
  c. have a latest start time equal to the largest of the earliest finish times for all activities entering the node.
  d. None of the alternatives is correct.

Question 2

In testing for the equality of k population means, the number of treatments is _____.
 a. k
  b. k-1
  c. nT
  d. nT - k



jaymee143

  • Sr. Member
  • ****
  • Posts: 341
Answer to Question 1

B

Answer to Question 2

d



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

HIV testing reach is still limited. An estimated 40% of people with HIV (more than 14 million) remain undiagnosed and do not know their infection status.

Did you know?

In 2012, nearly 24 milliion Americans, aged 12 and older, had abused an illicit drug, according to the National Institute on Drug Abuse (NIDA).

Did you know?

Since 1988, the CDC has reported a 99% reduction in bacterial meningitis caused by Haemophilus influenzae, due to the introduction of the vaccine against it.

Did you know?

Malaria mortality rates are falling. Increased malaria prevention and control measures have greatly improved these rates. Since 2000, malaria mortality rates have fallen globally by 60% among all age groups, and by 65% among children under age 5.

Did you know?

Acetaminophen (Tylenol) in overdose can seriously damage the liver. It should never be taken by people who use alcohol heavily; it can result in severe liver damage and even a condition requiring a liver transplant.

For a complete list of videos, visit our video library