Author Question: Activities following a node a. can begin as soon as any activity preceding the node has been ... (Read 119 times)

formula1

  • Hero Member
  • *****
  • Posts: 666
Activities following a node
 a. can begin as soon as any activity preceding the node has been completed.
  b. have an earliest start time equal to the largest of the earliest finish times for all activities entering the node.
  c. have a latest start time equal to the largest of the earliest finish times for all activities entering the node.
  d. None of the alternatives is correct.

Question 2

In testing for the equality of k population means, the number of treatments is _____.
 a. k
  b. k-1
  c. nT
  d. nT - k



jaymee143

  • Sr. Member
  • ****
  • Posts: 341
Answer to Question 1

B

Answer to Question 2

d



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Cucumber slices relieve headaches by tightening blood vessels, reducing blood flow to the area, and relieving pressure.

Did you know?

Certain rare plants containing cyanide include apricot pits and a type of potato called cassava. Fortunately, only chronic or massive ingestion of any of these plants can lead to serious poisoning.

Did you know?

Disorders that may affect pharmacodynamics include genetic mutations, malnutrition, thyrotoxicosis, myasthenia gravis, Parkinson's disease, and certain forms of insulin-resistant diabetes mellitus.

Did you know?

In the United States, congenital cytomegalovirus causes one child to become disabled almost every hour. CMV is the leading preventable viral cause of development disability in newborns. These disabilities include hearing or vision loss, and cerebral palsy.

Did you know?

The first monoclonal antibodies were made exclusively from mouse cells. Some are now fully human, which means they are likely to be safer and may be more effective than older monoclonal antibodies.

For a complete list of videos, visit our video library