Author Question: Activities following a node a. can begin as soon as any activity preceding the node has been ... (Read 61 times)

formula1

  • Hero Member
  • *****
  • Posts: 666
Activities following a node
 a. can begin as soon as any activity preceding the node has been completed.
  b. have an earliest start time equal to the largest of the earliest finish times for all activities entering the node.
  c. have a latest start time equal to the largest of the earliest finish times for all activities entering the node.
  d. None of the alternatives is correct.

Question 2

In testing for the equality of k population means, the number of treatments is _____.
 a. k
  b. k-1
  c. nT
  d. nT - k



jaymee143

  • Sr. Member
  • ****
  • Posts: 341
Answer to Question 1

B

Answer to Question 2

d



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Not getting enough sleep can greatly weaken the immune system. Lack of sleep makes you more likely to catch a cold, or more difficult to fight off an infection.

Did you know?

The term pharmacology is derived from the Greek words pharmakon("claim, medicine, poison, or remedy") and logos ("study").

Did you know?

Historic treatments for rheumatoid arthritis have included gold salts, acupuncture, a diet consisting of apples or rhubarb, nutmeg, nettles, bee venom, bracelets made of copper, prayer, rest, tooth extractions, fasting, honey, vitamins, insulin, snow collected on Christmas, magnets, and electric convulsion therapy.

Did you know?

There are more nerve cells in one human brain than there are stars in the Milky Way.

Did you know?

According to the CDC, approximately 31.7% of the U.S. population has high low-density lipoprotein (LDL) or "bad cholesterol" levels.

For a complete list of videos, visit our video library