Referring to the SPC chart signals that a process is out of control, what type of problem does each signal indicate? List the signals.
 
  What will be an ideal response?

Question 2

Which of the following is true about forecast bias?
 
  A) It is the mean absolute deviation.
  B) It is equal to the square root of the MSE.
  C) When it is negative it means that the forecasts tended to be high.
  D) When it is positive it means that the forecasts tended to be high.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

SeanoH09

  • Sr. Member
  • ****
  • Posts: 323
Answer to Question 1

The signals that something has changed are:
1. one or more points outside the control limits
2. nine or more points in a row above or below the center line
3. six or more points moving in the same direction (up or down)
4. 14 points in a row, alternating up and down.

The first signal means that something has caused the process to produce a higher (or lower) measure than would be normally expected. This could be a problem with variability or a jump one way or the other in the process center. Only one such point above or below the control limits is needed to reach the conclusion that a special cause situation exists.

The second signal implies that the process center is drifting up or down. For example, this type of situation could occur in a process that is sensitive to temperature. If for some reason temperature gradually is increasing, the output measure will gradually change with the temperature change.

The third signal indicates that the process average has shifted (higher or lower) due to some special circumstance. For instance, a control setting may have been changed causing the output measures to increase or decrease consistently.

The fourth signal indicates something is causing the process to change between measurements.

Answer to Question 2

C




Beheh

  • Member
  • Posts: 520
Reply 2 on: Jun 24, 2018
Great answer, keep it coming :)


meganmoser117

  • Member
  • Posts: 303
Reply 3 on: Yesterday
Gracias!

 

Did you know?

The first war in which wide-scale use of anesthetics occurred was the Civil War, and 80% of all wounds were in the extremities.

Did you know?

Approximately 25% of all reported medication errors result from some kind of name confusion.

Did you know?

The ratio of hydrogen atoms to oxygen in water (H2O) is 2:1.

Did you know?

Medication errors are more common among seriously ill patients than with those with minor conditions.

Did you know?

The immune system needs 9.5 hours of sleep in total darkness to recharge completely.

For a complete list of videos, visit our video library